SECTION 3: SETUP

Preparation

The list below outlines the basic process of pre- paring your machine for operation. Specific steps are covered later in this section.

The typical preparation process is as follows:

1.Unpack the lathe and inventory the contents of the box/crate.

2.Clean the lathe and its components.

3.identify an acceptable location for the lathe and move it to that location.

4.level the lathe and bolt it to the floor, or place it on leveling pads.

5.assemble the loose components and make any necessary adjustments or inspections to ensure the lathe is ready for operation.

6.Check lathe for proper lubrication.

7.Connect the lathe to the power source.

8.Test run lathe to ensure it functions properly.

9.perform the spindle break-in procedure to prepare the lathe for operation.

Unpacking

Your machine was carefully packaged for safe transportation. Remove the packaging materials from around your machine and inspect it. If you discover any damage, please call us immediately at (570) 546-9663 for advice.

Save the containers and all packing materials for possible inspection by the carrier or its agent. Otherwise, filing a freight claim can be difficult.

When you are completely satisfied with the condi- tion of your shipment, inventory the contents.

-20-

SUFFOCATION HAZARD!

Keep children and pets away from plastic bags or packing materials shipped with this machine. Discard immediately.

Needed for Setup

The following are needed to complete the setup process, but are not included with your machine.

For Lifting and Moving:

—a forklift or other power lifting device rated for at least 6800 lbs.

—two lifting straps rated for at least 6800 lbs. each­

—1" diameter x 49" long steel barstock­ —two people to guide machine

For Power Connection:

—A power source that meets the minimum cir- cuit requirements for this machine (review Power Supply on Page 18 for details)

—An electrician or qualified service person- nel to ensure a safe and code-compliant connection to the power source

For Assembly: —shop rags —Cleaner/degreaser (see Page 22) —Quality metal protectant lubricant —safety glasses for each person

—Floor mounting hardware as needed (see Page 25)

—precision level at least 1" long

Model G0746/G0749 (Mfg. Since 3/13)