b.Turn on the power supply (flip the AC switch to “I”) when ready to supply power to the switch. The switch automatically runs POST (power on self-test) each time it is turned on.

c.If the FC 16B includes a second power supply, repeat Steps 4a and 4b for the remaining power supply.

Note Do not connect the switch to the network until the IP address is correctly set. For instructions on how to set the IP address, see “Configuring and Connecting the Switch” on page 17.

Installing the Switch in a Rack

This section provides instructions for installing the FC 16B in an HP or

Compaq/Rittal rack.

Figure 1. FC 16B Rack-Mounted Switch

4

Quick Start Guide

Page 10
Image 10
HP A7340-96002 manual Installing the Switch in a Rack, FC 16B Rack-Mounted Switch