3.4.2 Project Plan Example
The actual schedule will be determined at Project 2 start, based on the
completion of the Project 1 Inventory Determination completion date, the
expected switchover date, and any potential conflicts with ABCs processing.

3.4.2.1 Project Plan - Summary

Task Name ID Projected Actual
Start End Start End
Preparation Phases 01 01/09/98 05/10/98
Application Inventory 02 01/09/98 03/10/98
Specifications 03 02/01/98 05/03/98
Customization 04 02/15/98 05/10/98
Conversion Phases 05 04/26/98 09/21/98
Trial Conversion 06 04/26/98 09/21/98
Online Testing 07 04/26/98 07/26/98
Batch Testing 08 05/10/98 09/13/98
Production Testing 09 08/16/98 09/21/98
Implementation Phases 10 09/01/98 10/15/98
Actual Conversion & Switchover 11 09/01/98 10/23/98
Initial MVS Operations 12 09/20/98 10/23/98
Migration Completion 10/23/98 10/23/98
56 VSE to OS/390 Migration Workbook