Preinstallation requirements

Standard 1.04

1Ensure that the server is laying on its side, supported to give the server bottom four to five inches clearance above the work surface.

2Attach the feet as shown in the preceding diagram.

Use four screws to attach each foot to the chassis. The holes in the feet line up with only one set of holes in the chassis, as follows:

„front foot: The middle hole is towards the front of the chassis.

„back foot: The middle hole is towards the back of the chassis.

3Place the server on its feet.

What’s next?

Continue with the hardware installation. For more information, see “Installation checklist” on page 34.