UPS SETUP

Unloading the Cabinet(s)

The following tools are required for unloading the cabinet(s):

S15 mm wrench or socket

S7 mm nutdriver or socket

C A U TION

The UPS and Extended Battery Module (EBM) are heavy (see page 8). Unloading the cabinets requires at least two people to safely remove the cabinets from the pallet.

To remove the UPS or EBM from the shipping pallet:

1.Remove the two M10 bolts securing the stabilizing bracket to the pallet (see Figure 2).

M10 Bolts

Figure 2. Removing the Stabilizing Bracket Bolts

2.Remove the four M4 screws securing the stabilizing bracket to the cabinet rear panel and remove the bracket (see Figure 3). Retain the hardware for later use.

NOTE Be sure to retain the stabilizing bracket and hardware for later re-assembly onto the cabinet.

EATON Powerware® 9155 Parallel UPS (8–15 kVA) User’s Guide S 164201592 Rev C www.powerware.com

9