PARALLEL INSTALLATION

10.Verify that each UPS battery circuit breaker is in the OFF position (see Figure 9).

Battery

ON

Connector

 

 

OFF

UPS Wiring

Battery Circuit Breaker

Access Cover

 

Conduit Landing

 

Figure 9. UPS Rear View (2-High Shown)

11.From each UPS, remove the UPS wiring access cover and retain (see Figure 9).

12.Hardwire the UPS input terminations (TB1-1 through TB1-5) for each UPS.

See Table 2 for specifications and Figure 10 for a detailed view of the UPS terminal block.