C H A P T E R 2
INSTALLATION SETUP
This chapter explains how to setup and install the Powerware 9170 cabinets:
Unpacking and setup, including clearances and location requirements
Caster cart installation
Stabilizer bracket installation (for
Floor anchor kit installation
Moving the cabinets
Equipment Clearances
All cabinet sizes require the following clearances to allow for servicing and adequate ventilation:
From the side panels: 6 (15.2 cm)
Top and back: 12 (30.5 cm)
Front: 36 (91.5 cm)
If flexible conduit connects the UPS to the service input and load distribution panels, you may be able to gain access for servicing by moving the UPS. If this is the case, you must still leave 12 (30.5 cm) clearance at the back and 6 (15.2 cm) at the sides of the UPS for ventilation.
NOTE Do not block the ventilation holes on each side and the back of the unit.
Nine- and
Powerware® 9170 User's Guide | 7 |