Installation Setup

Mounting Centers for 5/16￿ (8-mm) Floor Bolts

Dimension (see Figure 12)

Measurement

 

 

 

 

A

14.5￿ (36.8 cm)

 

 

B (3- and 6-slot cabinets)

30.25￿ (76.8 cm)

 

 

B (9- and 12-slot cabinets)

34.25￿ (87 cm)

 

 

 

B

Floor Anchor

Bracket

 

A

Figure 12. Floor Anchor Brackets Bolted to UPS Cabinet

Moving the Cabinets

The Powerware 9170 UPS and the battery cabinet are very heavy with power and battery modules installed. Before moving the cabinets, remove the power and battery modules and move these modules separately from the cabinets.

The smaller (3- and 6-slot) cabinets may be ordered with a caster cart, to enable moving the cabinet. •Caster Cart Installation" on page 10 describes how to set the four foot pads on this cart to keep the cabinet from rolling when properly positioned.

The larger (9- and 12-slot) cabinets have casters built into the cabinet base. Use the following procedure to raise the cabinet before rolling it on its casters. For 12-slot cabinets that do not have output isolation, see •Stabilizer Bracket Installation" on page 11, for details about mounting stabilizer brackets before rolling the cabinet into place.

1.Ensure that the cabinet contains no power or battery modules.

2.Locate the four plastic caps covering the caster bolts. They are at the corners of the cabinet base.