Installation Setup
Mounting Centers for 5/16
Dimension (see Figure 12) | Measurement |
|
|
|
|
A | 14.5 (36.8 cm) | |
|
| |
B (3- and | 30.25 (76.8 cm) | |
|
| |
B (9- and | 34.25 (87 cm) | |
|
|
|
B | Floor Anchor |
Bracket | |
| A |
Figure 12. Floor Anchor Brackets Bolted to UPS Cabinet
Moving the CabinetsThe Powerware 9170 UPS and the battery cabinet are very heavy with power and battery modules installed. Before moving the cabinets, remove the power and battery modules and move these modules separately from the cabinets.
The smaller (3- and
The larger (9- and
1.Ensure that the cabinet contains no power or battery modules.
2.Locate the four plastic caps covering the caster bolts. They are at the corners of the cabinet base.
Powerware® 9170 User's Guide | 15 |