Automation and Drives - SCE
4.6Loading to the CPU
The control program for the color mixing plant is not completed.
In the project window, highlight the folder Blocks and then click on the button “Load“
4.7Program Test
After loading the control program to the CPU, switch the controller to the RUN mode. Test your program. For example, at the tank blocks, you can monitor the levels. With “Monitor/control variables“, you can enter levels (MW120 to MW124).
Preface Installation Project Description Step7 Projekt HMI Station WinCC flexible Project Messages Recipes User Management
T I A Training Document | Page 33 of 129 | Module |
|
| F6 |
Issued: 02/2008 |
| Operator Control with WinCC flexible 2005 |