Start-up (without DC main switch)
1.Connect the Tyco Solarlok connectors to your Solar Inverter.
2.
Shut-down (with DC main switch)
1.Disconnect the PV generator side by opening the DC main switch.
2.Open the grid connection by isolating (switching off) the corresponding grid fuse.
3.After a waiting time of at least five minutes, the Solar Inverter is deener gised.
Shut-down (without DC main switch)
1.Interrupt the grid connection by isola- ting (switching off) the corresponding grid fuse. A fault will then be recorded in the fault memory of the Solar Inverter.
2.Pull the Tyco Solarlok connector out of your Solar Inverter.
!
Never disconnect the PV generator by pulling out the Tyco Solarlok connectors under load! Otherwise a powerful electric arc might damage the connectors.
The damaged connectors then have to be replaced!
GB
2.5Dismantling the Solar Inverter
To dismantle the Solar Inverter, loosen the hexagon socket screws, and move the cover up. Make sure the Solar Inverter is