11.1 UPS Connections

Terminal Blocks 100, 150, and 225kVA.

 

 

 

 

 

 

 

1

2

3

4

5

6

7

8

9

10

11

12

13

U V W U V W N U V W N

- +

AC INPUT

BYPASS INPUT

AC OUTPUT

BATTERY

3-phase 3-wire

3-phase 4-wire

3-phase 4-wire

 

The terminals shown are located at the bottom inside of the 150/225kVA UPS. External cable size is recommended in the Table 1 and 2.

Table 1 Recommended Cable Size and Tightening Torque for 150kVA UPS.

The tightening torque must be greater than 90 percent of the recommended torque.

Cable Size and Tightening Torque for 150kVA UPS (Only copper wires allowed)

Block Number

Cable Size

Tightening Torque

 

 

 

1

AWG 4/0 or larger

275 in-lbs

 

 

 

2

AWG 4/0 or larger

275 in-lbs

 

 

 

3

AWG 4/0 or larger

275 in-lbs

 

 

 

4

AWG 4/0 or larger

275 in-lbs

 

 

 

5

AWG 4/0 or larger

275 in-lbs

 

 

 

6

AWG 4/0 or larger

275 in-lbs

 

 

 

7

AWG 4/0 or larger

275 in-lbs

 

 

 

8

AWG 4/0 or larger

275 in-lbs

 

 

 

9

AWG 4/0 or larger

275 in-lbs

 

 

 

10

AWG 4/0 or larger

275 in-lbs

 

 

 

11

AWG 4/0 or larger

275 in-lbs

 

 

 

*12

Two 350MCM or larger

275 in-lbs

 

 

 

*13

Two 350MCM or larger

275 in-lbs

 

 

 

NOTE: Maximum cable size is 350MCM.

*One battery string (consult factory if using multiple battery strings).