Generac 13694330200 owner manual Maintenance Tasks

Page 23

 

 

 

Maintenance

 

 

 

 

Maint

Maintenance

Maintenance Tasks

Task Completed

level

Interval

Date/Initials

 

 

 

 

 

 

 

1. Disable the unit from operating per the first page warning.

 

 

 

 

 

 

 

2. Check the engine oil level. Adjust as necessary.

 

 

 

 

 

 

Every month

3. Check the engine coolant level. Adjust as necessary.

 

 

 

 

 

or

 

 

 

 

 

 

10 hours

4. Check the battery electrolyte level if accessible. Adjust as necessary.

 

 

of operation.

 

 

 

 

1

 

 

 

 

 

 

 

(Requires

5. Check the diesel fuel supply level. Adjust as necessary.

 

 

approximately

 

 

 

 

 

0.5 man hours

 

 

 

per unit)

6. Check the air inlets and outlets for debris. Clean as necessary.

 

 

 

 

 

 

 

 

 

 

7. Visually inspect the unit looking for leaks, wear or damage, loose

 

 

 

connections or components, and corrosion. Correct as necessary.

 

 

 

 

 

 

 

8. Return the unit to operational condition.

 

 

 

 

 

Technician'sSignature

Date Inspection Completed

Unit Hour Meter Reading at Completion of the Inspection

21

Image 23
Contents @us Table of Contents Introduction Authorized Service Dealer LocationOperation and Maintenance HOW to Obtain ServiceGeneral Hazards Electrical Hazards Generator SET XPL Label Identification RecordData Label DC Fuses Equipment DescriptionEngine Protective Devices Fuel System SpecificationsFuel System Reduirements and Recommendations Battery InstallationConnections BatteryGenerator AC Lead Field Wiring Requirements Table SIX-LEAD VAG, THREE-PHASE StatorStarting Aids Field Wiring Connections to Buss BarsGenerator and Load Compatibility Engine Coolant Heaters ~KE~Battery Chargers Battery Warmers OptionalOther Published Standards Nfpa StandardsGrounding the Generator Transfer Switch Start Signal ConnectionsEmergency Circuit Isolation Method Total Circuit Isolation MethodPrior to Initial START-UP Preparation Before START-UPVented Batteries Engine STA8T-UP and TRANSFE8 Operating Unit with Manual Transfer SwitchGenerator Control and Operation Retransfer and Shutdown Transfer SwitchService Schedule Annually or Every 600 Hours whichever comes first Periodic MaintenanceInspect Exhaust System Repair PartsHOW to Order Parts Check FluidsService Maintenance Interval Information Maintenance Tasks Maint Maintenance Maintenance Tasks Task Completed Maint Maintenance Maintenance Tasks Task Completed Maint Maintenance Maintenance Tasks Task Completed Level Maintenance Tasks Task Completed TechniciansSignature Warranty California and Federal Emission Control Warranty Statement Warranty Groupb Groupb 34h ~tJ· ~tJ Grouph Grouph Exploded View EV, CB Mounting KIT MDl Drawing # OJl027 Group a Group a ~ //rY Exploded View EV Altcomprt 80KW DD PME G17 Drawing # OJ1481 Applicable to PART# This page Left Intentionally Blank Group a MAIN, ALT Tower 390 Long 10 390 Alternator Single CIS 390/520 Alternator Dual CIS Load CENTER,125A,SIEMENS 8 BAY\ Group B Blank 171\\ PART# QTY Description QTY Date 7/27//11 Exploded View Drawing # OH5043D Group H Drawing # OH5043D Part Date 2/25/10 FAN Guard R/H Side GROUpe GROUpe 111 GROUpe 180 Basetank CD0095U1N Type GROUpe GROUpe Groupd Groupd ~14 Reducer Hump 18\\ Groupf Groupf Groupf 3 of4 This page left blank intentionally ~-+-+ + + This page is Left Intentionally Blank Groupg Groupg ~ o ===~ ~ o DO-~~ ~ o Nl ---+ + + + 1 Groupg Groupg ~~r= ~~~~WHtjITEt=~= ~S NC RB3 ~~~~~~ 5005~ ~fi Ir~ Drawing # OH9863 ~~BR2DB Drawing # OH9863 Group H This page is Left Intentionally Blank 2ASSEMBY View for Shroud OH78890ST03 only QTY Description RevisionH-6657-C 1of Clamp Hose 7/8 00 Double Wire Date 2/12/10 Washer Date 3/21/10 Drawing No. OH8028 Junction BOX Alternate Dual Battery Configuration Battery Heater Connection Rl.·1 Drawing # OJI047 Page JNI ISWEU.SAS tl3MOd ,,Jdtl3N3EJ