AEG Thyro-P 2.2 SET POINT CONTROL CHARACTERISTIC

Page 16

16

Mains load optimization (ASM procedure)

For systems in which several Power Controllers are employed in full wave switch mode TAKT, it is

possible that individual Power Controllers are synchronized so that a regular mains load is achieved 

by defi ned switching of the individual Power Controller in sequence. This avoids load peaks by 

random simultaneous switching of many Power Controllers and load troughs are fi lled up. The

upstream transformer and/or the upstream feed point may be designed for a lower load. Besides

savings in investment and operating cost, lower mains reactions also result.

2.2 SET POINT CONTROL CHARACTERISTIC

The set point control characteristic of Thyro-P may be easily adapted for the control output signal

of the upstream process controller or automation system. All signals customary on the market may 

be used. The adaption is made by changing the starting and ending points of the control characte-

ristic. Inverted operation (ending value is smaller than the starting value in voltage or current) is also 

possible.

The effective set point is the total set point. It is formed by adding the four set points as shown in 

fi g. 2.

In the simplest case all the set point values are added algebraically. The prerequisite for a set point

to infl uence the total set point value is that it must be enabled by the set point Enable Register.

•

 Set point 1

 (X5.2.10 - X5.1.13 ground) 0-20mA default

• 

Set point 2

 (X5.2.11 - X5.1.13 ground) 0-5V default

The inputs set point 1, 2 are two electrically equal analogue inputs for current or voltage signals,

with subsequent A/D converter (resolution 0.025% of the fi nal value), and they may be set to the

following signal ranges:

0(4)-20 mA   (Ri about 250

⍀

) 

max. 24mA 

siehe ”

ATTENTION“

0-5       V  

(Ri about 8,8k

⍀

) max. 

12V

0-10     V  

(Ri about 5k

⍀

)

max. 

12V

The following table shall be used for the hardware confi guration of the set point inputs (see also

FILE COMPONENT MOUNTING DIAGRAM CONTROL DEVICE, fi gure 10). If the hardware con-

fi guration is changed, the Thyro-P parameters must be changed accordingly with the LBA or the 

Thyro-Tool.

X221 for Set point input 1   

 

Bridge X221 

Signal range 

Set point input 1

 

closed*

0(4) 

-20mA

 (X5.2.10)

 

open 

0-5V / 0-10V 

(X5.2.10)

X222 for Set point input 2   

 

Bridge X222 

Signal range 

Set point input 2

 closded 

0(4)-20mA  

(X5.2.11)

 

open*

0-5V

 / 0-10V 

(X5.2.11)

                    * default

ATTENTION

If the open-circuit voltage of the connected set point exceeds 12V in the 20mA signal range, the 

set point inputs can be destroyed, if the belonging bridge (X221, X222) is open. 

Within the stated input ranges, these values with the control characteristic may be adjusted to any

common signal characteristic.

Image 16