AEG Thyro-P 4.4 RESET, 4.4.1 SOFTWARE-RESET, 4.5 CONTROLLER LOCK

Page 39

39

ATTENTION

The ventilator must run when the Power Controller is switched on.

4.4 RESET

The input RESET (terminals X5.2.12-X5.1.14) is separated from the remaining system by an opto- electronic coupler. By opening the RESET jumper the Thyristor Power Controller is locked (load: 24V/20mA), i.e. the power sections are no longer triggered. On activating RESET, LED “ON” lights up red.

Functional procedure:

 

TERMINALS

FUNCTION

X5.12-14 closed

Enables the power sections, Power Contr. in operation

X5.12-14 open

Power Controller out of operation, communication via interfaces not

 

possible

X5.12-14

system reinitialisation

 

is closed

TAB. 12 RESET

 

The hardware RESET must be applied when synchronising the software of several Power Controllers (chapter 6.2 Software synchronisation). If the Power Controller is equipped with a Bus option, a Bus RESET also ensues from the hardware RESET. Apart from opening the jumper terminal X5.2.12- X5.1.14, the hardware RESET is also activated by supply voltage OFF or by reducing the supply voltage at the Power Controller (A70-X1) to below 160V.

4.4.1 SOFTWARE-RESET

The RESET function can be activated by signals via the status register (software RESET). The soft- ware RESET does not influence the Bus function.

4.5 CONTROLLER LOCK

The input controller lock (terminals X5.2.15 and X5.1.14) is electrically identical to the input RESET (electrical data as under 4.4.).

ATTENTION

When activating controller lock, the LED „PULSE LOCK“ is lit and the control device remains com- pletely in operation. The total set point is therefore without effect, but the min. limiting values (TS- MIN, HIME) remain active. This enables securing a certain quantity of electrical energy at the load.

TERMINALS

FUNCTION

X5.15-14 closed

Power Controller operating

X5.15-14 open

control pulses OFF (default value) or pulse limit

TAB. 13 CONTROLLER LOCK

 

All other functions of the Power Controller remain in operation. The state of the signalling relay does not change (parameter-dependent) and communications remains active. After closing the controller lock jumper, the controller is back in operation.

Image 39