CoolTherm

Manual / Bedienungsanleitung

6.Servicing and maintenance

Servicing and maintenance work is to be performed by correctly trained personnel only and in accordance with applicable regulations as well as manufacturers’ specifications!

Only use original spare parts that have been tested and approved by the manufacturer.

(If necessary, request a comprehensive spare parts list from the manufacturer)

For cleaning use commercially available cleaning agents only. Follow the stipulated safety measures and do not use any tools that may cause scratching or tools for scraping (surface treatment will be irreversibly damaged!)

Prior to all servicing work:

-Correctly shut down fans and any other electrical components and disconnect from the electricity supply!

-Wait until the fan blades have stopped!

-Secure against switch on!

-Shut down water cooling circuit and secure against switch on.

General inspection on fans (annually)

-Check for unusual bearing noises. (Check for excessive bearing play)

Replacement of fans (expected service life is approx. 40.000 operating hours at a temperature of 40°C / 104°F).

1.Remove the housing cover from the unit (with earth cable)

2.Check out which fan is failed, check the surface temperature of the fan e.g. and switch of the regarding fuse on the front side

3.Disconnect supply cable at the fan terminal block

4.Undo the four fastening bolts for the fan to be replaced.

5.Remove the failed fan.

CoolTherm

01_998_330_0_k

page / Seite 29/83

Image 31
Contents Liebert XDK-WRack Enclosure With Integrated Liquid Cooling Page Manual CoolTherm CoolTherm ContentsAbstract Safety Work safety symbolsSafety instructions Correct use Operating conditionsDescription General function Principle of operation of cooling Bottom plate with cutouts Rear Front DimensionsFront side / Seite 10/83 Useable space for server Chilled water Technical dataGeneral data Data overview CoolTherm Table aData overview CoolTherm Table B Hydraulic Data PDU Box ControlFan control characteristic factory setting Storage and transportation 680 kg Safety instruction for crane transport 680 kgCheck unit for transport damage Installation and commissioning Preparation for installationPositioning the units Adjustable Feet Remove recirculation air duct transport lockPreparing heat exchanger for initial commissioning Chilled water connection/ Seite 22/83 Condensed water connection Preparations for connectingHeat exchanger connection Electrical connection Automatic door opening Sealing of cabinetFunction Release of Automatic Door Opening Initial Commissioning Manual opening Manual closingTechnichal Data General inspection on fans annually Servicing and maintenanceRegularly inspect the heat exchanger annually Fan is installed in the reverse order of removalReplacement of Heat Exchanger Dismantling and disposal Customer service, manufacturers addressAppendix Quality requirements on the water used in CoolTherm Checked performed Completed Comments Checklist for unit installationGeneral data Client/Setup siteConfiguration Commissioning certificateGeneral condition Control of statusChilled water facility on site Electrical data / Documents Function checkMechanical functions Thermal checks Electrical functionsWater flow rate adjusted Yes Flow rate …………. l / min KW CoolTherm at 1.72m³/h chilled water flow rate CoolTherm Diagrams25kW-CoolTherm at 3.58m³/h chilled water flow rate Control Standard Factory SettingsSeite InhaltAllgemein Sicherheit Arbeitssicherheits SymboleSicherheitshinweis / Seite 45/83 Bestimmungsgemäße Verwendung EinsatzbedingungenBeschreibung Allgemeine Funktion Funktionsprinzip Kühlung Bodenplatte mit Öffnungen für Durchführungen Hinten Vorn AbmessungenFrontseite / Seite 51/83 Nutzbare Länge für Server / Einbauten Kühlwasser Technische DatenAllgemeine Daten Datenübersicht CoolTherm Tabelle aDatenübersicht CoolTherm Tabelle B Hydraulische Daten CoolTherm Vordersansicht RegelungKennlinie Lüfterregelung Werkseinstellung Lagerung und Transport Sicherheitshinweis für Krantransport 680 kg Gerät auf Transportschäden überprüfen Montage und Inbetriebnahme Vorbereitung zur MontageEinstellbare Füße Aufstellung der GeräteTransportsicherung der Luftumlenkung entfernen Anschluss KühlwasserZur Ventilkontrolle Kühleranschluss Vorbereitung für Anschluss Anschluss KondensatAbdichtung Gehäuse Anschluss ElektroFunktion Automatische TüröffnungAuslösung der Türöffnung Manuelles Schließen Erste InbetriebnahmeManuelles Öffnen Wartung und InstandhaltungTechnische Daten Lüfter austauschen Allgemeine Kontrollen an Ventilatoren jährlichAuswechseln des Wärmetauschers Allgemeine Kontrollen am Kühler jährlichDemontage und Entsorgung Kundendienst, Herstelleradressen / Seite 75/83 Durchgeführte Überprüfung Erledigt Checkliste zur GeräteaufstellungKonfiguration InbetriebnahmeprotokollAllgemeine Angaben Kunde/AufstellungsortAllgemeiner Zustand ZustandskontrolleKühlwasseranlage im Objekt Funktionskontrolle Mechanische Funktionen Elektrische Daten / DokumenteThermodynamische Überprüfungen Elektrische FunktionenVolumenstrom …………. l / min CoolTherm Kennlinien Werkseinstellungen der Regelung Page Page Web Site Monitoring Single-Phase UPS