5.Installation and commissioning

5.1Preparation for installation

Before you install the unit, you have to check a number of points. These checks are for safety and to ensure the correct function of the server cabinet. Take care when performing these checks

to ensure that the unit functions correctly.

Check unit for transport damage:

The packaging for the CoolTherm must not show signs of transport damage on delivery. Any damage on the packaging indicates possible transport damage.

In the worst case this damage may result in the loss of function.

Returning the unit in case of transport damage:

If the unit is not returned in the original packaging, the packaging used for return must comply with following criteria:

There must be at least 30 mm space between the unit and the packaging.

As an installation aid, there is a checklist in the appendix, that you should complete prior to commissioning.

The commissioning also can be carried out by approved staff. Use the commissioning certificate included in the appendix for this purpose.

CoolTherm must be installed on a level surface.

For this reason, check the horizontal alignment with a spirit level prior to starting installation.

Note that the floor must be able to support a rack load of 1.500 kg/m² (with installed equipment per CoolTherm).

To achieve good air circulation, ensure that

in the area of the equipment

in the area of the heat exchanger

in the air inlet

in the air outlet

there is no packaging material or other equipment that could hinder or prevent air circulation

CoolTherm

01_998_330_0_k

page / Seite 19/83

Image 21
Contents Liebert XDK-WRack Enclosure With Integrated Liquid Cooling Page Manual CoolTherm CoolTherm ContentsAbstract Safety Work safety symbolsSafety instructions Correct use Operating conditionsDescription General function Principle of operation of cooling Bottom plate with cutouts Rear Front DimensionsFront side / Seite 10/83 Useable space for server Chilled water Technical dataGeneral data Data overview CoolTherm Table aData overview CoolTherm Table B Hydraulic Data PDU Box ControlFan control characteristic factory setting Storage and transportation 680 kg Safety instruction for crane transport 680 kgCheck unit for transport damage Installation and commissioning Preparation for installationPositioning the units Adjustable Feet Remove recirculation air duct transport lockPreparing heat exchanger for initial commissioning Chilled water connection/ Seite 22/83 Preparations for connecting Condensed water connectionHeat exchanger connection Electrical connection Sealing of cabinet Automatic door openingFunction Release of Automatic Door Opening Initial Commissioning Manual closing Manual openingTechnichal Data General inspection on fans annually Servicing and maintenanceRegularly inspect the heat exchanger annually Fan is installed in the reverse order of removalReplacement of Heat Exchanger Dismantling and disposal Customer service, manufacturers addressAppendix Quality requirements on the water used in CoolTherm Checked performed Completed Comments Checklist for unit installationConfiguration Client/Setup siteCommissioning certificate General dataControl of status General conditionChilled water facility on site Function check Electrical data / DocumentsMechanical functions Thermal checks Electrical functionsWater flow rate adjusted Yes Flow rate …………. l / min KW CoolTherm at 1.72m³/h chilled water flow rate CoolTherm Diagrams25kW-CoolTherm at 3.58m³/h chilled water flow rate Control Standard Factory SettingsSeite InhaltAllgemein Sicherheit Arbeitssicherheits SymboleSicherheitshinweis / Seite 45/83 Bestimmungsgemäße Verwendung EinsatzbedingungenBeschreibung Allgemeine Funktion Funktionsprinzip Kühlung Bodenplatte mit Öffnungen für Durchführungen Hinten Vorn AbmessungenFrontseite / Seite 51/83 Nutzbare Länge für Server / Einbauten Kühlwasser Technische DatenAllgemeine Daten Datenübersicht CoolTherm Tabelle aDatenübersicht CoolTherm Tabelle B Hydraulische Daten CoolTherm Vordersansicht RegelungKennlinie Lüfterregelung Werkseinstellung Lagerung und Transport Sicherheitshinweis für Krantransport 680 kg Gerät auf Transportschäden überprüfen Montage und Inbetriebnahme Vorbereitung zur MontageEinstellbare Füße Aufstellung der GeräteTransportsicherung der Luftumlenkung entfernen Anschluss KühlwasserZur Ventilkontrolle Kühleranschluss Vorbereitung für Anschluss Anschluss KondensatAbdichtung Gehäuse Anschluss ElektroFunktion Automatische TüröffnungAuslösung der Türöffnung Manuelles Schließen Erste InbetriebnahmeWartung und Instandhaltung Manuelles ÖffnenTechnische Daten Lüfter austauschen Allgemeine Kontrollen an Ventilatoren jährlichAuswechseln des Wärmetauschers Allgemeine Kontrollen am Kühler jährlichDemontage und Entsorgung Kundendienst, Herstelleradressen / Seite 75/83 Durchgeführte Überprüfung Erledigt Checkliste zur GeräteaufstellungAllgemeine Angaben InbetriebnahmeprotokollKunde/Aufstellungsort KonfigurationZustandskontrolle Allgemeiner ZustandKühlwasseranlage im Objekt Funktionskontrolle Mechanische Funktionen Elektrische Daten / DokumenteThermodynamische Überprüfungen Elektrische FunktionenVolumenstrom …………. l / min CoolTherm Kennlinien Werkseinstellungen der Regelung Page Page Web Site Monitoring Single-Phase UPS