Liebert XDK-W user manual Dismantling and disposal, Customer service, manufacturers address

Page 34

CoolTherm

Manual / Bedienungsanleitung

The heat exchanger is installed in the reverse order of removal.

Regularly check the condensed water drain and clean if necessary

7.Dismantling and disposal

The CoolTherm may be dismantled by suitably qualified personnel only.

Prior to dismantling:

-Correctly shut down fans and any other electrical components and disconnect from power supply!

-Secure against switch on!

-Shut down water cooling circuit and secure against switch on.

Disconnect the unit from the external water circuit by closing the shut-off valves and drain the water circuit in the unit.

Transport the unit as described in "Transportation" section using a lifting device with sufficient load bearing capacity.

Dispose of the air-conditioner as per the locally applicable disposal and safety instructions. We recommend using a specialist recycling organisation. All parts can be stripped down and consist of:

-aluminium, steel, brass, copper

-labelled plastic parts

-electronic parts

8.Customer service, manufacturer's address

All Knürr products are subject to continuous quality control and comply with applicable regulations. For all questions that you may have in relation to our products, please contact the provider of your server cabinet system or contact directly:

Knürr AG

Raubaer Strasse 1

01623 Lommatzsch

Tel.: +49 (0) 800 000 6295

Email: service@knuerr.com

CoolTherm

01_998_330_0_k

page / Seite 32/83

Image 34
Contents Liebert XDK-WRack Enclosure With Integrated Liquid Cooling Page Manual CoolTherm Contents CoolThermSafety Work safety symbols AbstractSafety instructions Operating conditions Correct useDescription General function Principle of operation of cooling Dimensions Bottom plate with cutouts Rear FrontFront side / Seite 10/83 Useable space for server Technical data Chilled waterData overview CoolTherm Table a General dataData overview CoolTherm Table B Hydraulic Data Control PDU BoxFan control characteristic factory setting Storage and transportation Safety instruction for crane transport 680 kg 680 kgInstallation and commissioning Preparation for installation Check unit for transport damageAdjustable Feet Remove recirculation air duct transport lock Positioning the unitsChilled water connection Preparing heat exchanger for initial commissioning/ Seite 22/83 Condensed water connection Preparations for connectingHeat exchanger connection Electrical connection Automatic door opening Sealing of cabinetFunction Release of Automatic Door Opening Initial Commissioning Manual opening Manual closingTechnichal Data Servicing and maintenance General inspection on fans annuallyFan is installed in the reverse order of removal Regularly inspect the heat exchanger annuallyReplacement of Heat Exchanger Customer service, manufacturers address Dismantling and disposalAppendix Quality requirements on the water used in CoolTherm Checklist for unit installation Checked performed Completed CommentsCommissioning certificate Client/Setup siteConfiguration General dataGeneral condition Control of statusChilled water facility on site Electrical data / Documents Function checkMechanical functions Electrical functions Thermal checksWater flow rate adjusted Yes Flow rate …………. l / min CoolTherm Diagrams KW CoolTherm at 1.72m³/h chilled water flow rateControl Standard Factory Settings 25kW-CoolTherm at 3.58m³/h chilled water flow rateInhalt SeiteSicherheit Arbeitssicherheits Symbole AllgemeinSicherheitshinweis / Seite 45/83 Einsatzbedingungen Bestimmungsgemäße VerwendungBeschreibung Allgemeine Funktion Funktionsprinzip Kühlung Abmessungen Bodenplatte mit Öffnungen für Durchführungen Hinten VornFrontseite / Seite 51/83 Nutzbare Länge für Server / Einbauten Technische Daten KühlwasserDatenübersicht CoolTherm Tabelle a Allgemeine DatenDatenübersicht CoolTherm Tabelle B Hydraulische Daten Regelung CoolTherm VordersansichtKennlinie Lüfterregelung Werkseinstellung Lagerung und Transport Sicherheitshinweis für Krantransport 680 kg Montage und Inbetriebnahme Vorbereitung zur Montage Gerät auf Transportschäden überprüfenAufstellung der Geräte Einstellbare FüßeAnschluss Kühlwasser Transportsicherung der Luftumlenkung entfernenZur Ventilkontrolle Kühleranschluss Anschluss Kondensat Vorbereitung für AnschlussAnschluss Elektro Abdichtung GehäuseAutomatische Türöffnung FunktionAuslösung der Türöffnung Erste Inbetriebnahme Manuelles SchließenManuelles Öffnen Wartung und InstandhaltungTechnische Daten Allgemeine Kontrollen an Ventilatoren jährlich Lüfter austauschenAllgemeine Kontrollen am Kühler jährlich Auswechseln des WärmetauschersDemontage und Entsorgung Kundendienst, Herstelleradressen / Seite 75/83 Checkliste zur Geräteaufstellung Durchgeführte Überprüfung ErledigtKunde/Aufstellungsort InbetriebnahmeprotokollAllgemeine Angaben KonfigurationAllgemeiner Zustand ZustandskontrolleKühlwasseranlage im Objekt Elektrische Daten / Dokumente Funktionskontrolle Mechanische FunktionenElektrische Funktionen Thermodynamische ÜberprüfungenVolumenstrom …………. l / min CoolTherm Kennlinien Werkseinstellungen der Regelung Page Page Web Site Monitoring Single-Phase UPS