Liebert XDK-W user manual Control Standard Factory Settings

Page 43

CoolTherm

Manual / Bedienungsanleitung

25kW-CoolTherm at 3.58m³/h chilled water flow rate

 

40 kW

 

 

 

 

 

 

 

 

35 kW

 

 

 

 

 

20°C supply air temperature 1)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

22°C supply air temperature 1)

 

30 kW

 

 

 

 

 

25°C supply air temperature 1)

capacity

25 kW

 

 

 

 

 

 

 

20 kW

 

 

 

 

 

 

 

cooling

 

 

 

 

 

 

 

15 kW

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

10 kW

 

 

 

 

 

 

 

 

5 kW

 

 

 

 

 

 

 

 

0 kW

 

 

 

 

 

 

 

 

10,0 °C

12,0 °C

14,0 °C

16,0 °C

18,0 °C

20,0 °C

22,0 °C

24,0 °C

chilled water supply temperature [°C]

9.5Control Standard Factory Settings

start of fan rotation

10°C (start with 75% rotation)

fan speed control

20 – 23°C (75% - 100% rotation)

start of 3-way valve

10°C (start with closed position)

control of 3way valve

16 – 19°C (0 – 100% control water flow rate)

front LED yellow

temperature alarm >26°C or rear door open

front LED red

temperature alarm >26°C and rear door open

automatic door opening

door release at 35°C

Note:

All settings could vary by project.

CoolTherm

01_998_330_0_k

page / Seite 41/83

Image 43
Contents Liebert XDK-WRack Enclosure With Integrated Liquid Cooling Page Manual CoolTherm CoolTherm ContentsAbstract Safety Work safety symbolsSafety instructions Correct use Operating conditionsDescription General function Principle of operation of cooling Bottom plate with cutouts Rear Front DimensionsFront side / Seite 10/83 Useable space for server Chilled water Technical dataGeneral data Data overview CoolTherm Table aData overview CoolTherm Table B Hydraulic Data PDU Box ControlFan control characteristic factory setting Storage and transportation 680 kg Safety instruction for crane transport 680 kgCheck unit for transport damage Installation and commissioning Preparation for installationPositioning the units Adjustable Feet Remove recirculation air duct transport lockPreparing heat exchanger for initial commissioning Chilled water connection/ Seite 22/83 Condensed water connection Preparations for connectingHeat exchanger connection Electrical connection Automatic door opening Sealing of cabinetFunction Release of Automatic Door Opening Initial Commissioning Manual opening Manual closingTechnichal Data General inspection on fans annually Servicing and maintenanceRegularly inspect the heat exchanger annually Fan is installed in the reverse order of removalReplacement of Heat Exchanger Dismantling and disposal Customer service, manufacturers addressAppendix Quality requirements on the water used in CoolTherm Checked performed Completed Comments Checklist for unit installationGeneral data Client/Setup siteConfiguration Commissioning certificateGeneral condition Control of statusChilled water facility on site Electrical data / Documents Function checkMechanical functions Thermal checks Electrical functionsWater flow rate adjusted Yes Flow rate …………. l / min KW CoolTherm at 1.72m³/h chilled water flow rate CoolTherm Diagrams25kW-CoolTherm at 3.58m³/h chilled water flow rate Control Standard Factory SettingsSeite InhaltAllgemein Sicherheit Arbeitssicherheits SymboleSicherheitshinweis / Seite 45/83 Bestimmungsgemäße Verwendung EinsatzbedingungenBeschreibung Allgemeine Funktion Funktionsprinzip Kühlung Bodenplatte mit Öffnungen für Durchführungen Hinten Vorn AbmessungenFrontseite / Seite 51/83 Nutzbare Länge für Server / Einbauten Kühlwasser Technische DatenAllgemeine Daten Datenübersicht CoolTherm Tabelle aDatenübersicht CoolTherm Tabelle B Hydraulische Daten CoolTherm Vordersansicht RegelungKennlinie Lüfterregelung Werkseinstellung Lagerung und Transport Sicherheitshinweis für Krantransport 680 kg Gerät auf Transportschäden überprüfen Montage und Inbetriebnahme Vorbereitung zur MontageEinstellbare Füße Aufstellung der GeräteTransportsicherung der Luftumlenkung entfernen Anschluss KühlwasserZur Ventilkontrolle Kühleranschluss Vorbereitung für Anschluss Anschluss KondensatAbdichtung Gehäuse Anschluss ElektroFunktion Automatische TüröffnungAuslösung der Türöffnung Manuelles Schließen Erste InbetriebnahmeManuelles Öffnen Wartung und InstandhaltungTechnische Daten Lüfter austauschen Allgemeine Kontrollen an Ventilatoren jährlichAuswechseln des Wärmetauschers Allgemeine Kontrollen am Kühler jährlichDemontage und Entsorgung Kundendienst, Herstelleradressen / Seite 75/83 Durchgeführte Überprüfung Erledigt Checkliste zur GeräteaufstellungKonfiguration InbetriebnahmeprotokollAllgemeine Angaben Kunde/AufstellungsortAllgemeiner Zustand ZustandskontrolleKühlwasseranlage im Objekt Funktionskontrolle Mechanische Funktionen Elektrische Daten / DokumenteThermodynamische Überprüfungen Elektrische FunktionenVolumenstrom …………. l / min CoolTherm Kennlinien Werkseinstellungen der Regelung Page Page Web Site Monitoring Single-Phase UPS