Ad (6): Remote Link for up to 99 Solar

Inverters

If you wish to connect several Solar Inverters to the remote monitoring system, the individual Solar Inverters must be cross- linked via RS485. The RS485 signal of the first Solar Inverter in the row is transferred into the interface transformer with the fol- lowing allocation: «RS485 +» to «DATA+» and «RS485 to «DATA-». Connect the remote modem to the interface transfor- mer. With the last Solar Inverter, the jum- per «RS485 MATCH» must be closed. With all other Solar Inverters, it has to be in the open position.

￿!

To identify the individual Solar Inverters,

a clear RS485 has to be assigned to each of them. See chapter «Setting the RS485 Address».

Finding the Jumper «RS485 MATCH»

in the Solar Inverter

Please make sure the jumper «RS485 MATCH» is in the right position, considering the communication interconnection you have chosen. This jumper is on the under- side of the interface circuit board.

Illustr.: Position of the jumper «RS485

MATCH»

138

Image 54
Contents Sunways Solar Inverter NT Solar Installation Safety InstructionsBasic Settings Sunways Solar InverterOperating the Display Configuration of the Solar InverterDismantling the Solar Inverter Internal Data MemoryTyco Solarlok Connectors Error DisplayError Diagnosis Abbreviations Technical Data NTGeneral information General Safety Instructions Opening the Device Sunways Solar Inverter NT Scope of DeliveryChecking the Consignment Page Standard Components of a PV System Standard components of the PV systemStructure of NT Page Error No Description Error DescriptionProtection Concept Page Installation Instructions Electrical Safety Mechanical SafetyCleaning Instructions Basic Settings Fixed voltage level 420 540Country Settings Page Ceiling 300 mm Min mm · Thermal Interaction · Protection from Moisture and Foreign ObjectsMechanical Installation Grid Connection DC+ USBThree-phase grid connection 25 aPage Connecting the PV Generator · Preparation · Connection Important InformationPage Communication Interfaces · RS485 Wiring · Connecting a cable to the spring-loaded terminalSpare RS485MATCH RS485GND Connecting the Alarm Relay · Important InformationParalleled alarm relays of several Solar Inverters Alarm relay terminal allocationConnecting the Insolation Temperature Sensor · Allocation of the cable terminal block Sensor pin nameSolar inverter pin name Start-up with DC main switch Commissioning the Solar InverterStarting-Up and Shutting-Down Solar Inverter Start-up without DC main switch Shut-down with DC main switchShut-down without DC main switch Operating Instructions · Setting Values · Menu Guide· Navigating with the Arrow Keys Page Page Configuring the Solar Inverter Internal Data Memory Sunways Monitor 2.0 Software Sunways Portal and Sunways Communicator Modem LinkInterface Cables Interface TransformerLink SunwaysMonitor Direct Monitor Local134 Modem Ad 5 Local Link for up to 99 Solar Inverters Spare RS485MATCH USBInverter 3 RS485 Ad 6 Remote Link for up to 99 Solar Inverters Finding the Jumper «RS485 MATCH» Solar InverterErrors 001 to Errors 004 toErrors 010 to Errors 007 toErrors 013 to ErrorErrors 017 to Errors 020 toErrors 023 to Errors 031 to Errors 028 toErrors 034 to Illustr. Operation indicator LED 143 Error Causes RemediesErrorCauses Remedies Error Causes ErrorCauses Error Causes Error Causes Error Causes 152 Appendix Tyco Solarlok Connectors Page LCD Designation Description MPPTechnical Data NT 10000 Model Solar Inverter NT159 Conformity and Safety Declarations 161 162 Terms and Conditions of Guarantee · Duration of Guarantee· Conditions · Exclusion of Liability General Exclusion of Liability All rights reserved. Sunways AGRegistered trademark Version 11/05