American Power Conversion PD150L6F, PD150G6F manual Configuring the InfraStruXure Manager

Page 44

Configuring the InfraStruXure Manager

Connect the InfraStruXure PDU to the InfraStruXure Manager

1.Connect a Cat-5 network cable to the surge-protected ethernet port on the PDU user connection plate.

You can make connections from

inside the enclosure, or you can remove the user connection plate and make your connections.

Remove the plate using a Phillips

or standard screw driver to loosen the two captive screws. Use the

knockout in the plate to route cables to and from the user

connections on the plate. If you remove the plate, make sure that

you do not disturb the existing connections.

2.Run the connected Cat-5 network cable through the knockout in the user connection plate to the InfraStruXure Manager Hub.

3.Once all APC InfraStruXure-Certified equipment is installed, the network cables are connected to the InfraStruXure Manager Hub, and start-up of the system is complete, configure the InfraStruXure Manager.

For detailed configuration instructions, see the InfraStruXure Manager Installation and Quick-Startmanual included with your InfraStruXure Manager.

See also

36

150kW InfraStruXure PDU—Operation and Configuration

Image 44
Contents 150kW InfraStruXure PDU Page About this Manual Page Contents Operation Customizing and Updating the PDU Product Information Overview Safety symbols used in this manualCross-reference symbols used in this manual Installation/maintenance Receiving/movingTotal power off procedure Emergency Power Off EPOEMI Overview InfraStruXure PDU ComponentsInfraStruXure PDU Front viewFront view interior Rear view Rear view interior PDU monitoring unit Left = 43..83 lower right = User connection plate PDU Display Interface Navigating through screens Top-level status screensTop-level menu screen Password-protected screens Power Factor Load-Meter ScreenVolt-Meter Screen Contacts Screen Input ContactsOpen or Closed Relay OutputsAlarm Relay Map How to connect contacts to the PDU monitoring unit Breakers Screen Main InputAlarms Screen New Logged ItemsEntire Log Clear LogGlobal Alarm ConfigLoading Limits Voltage LimitsPDU Alarms Alarm Condition ExplanationBranch Ckt Limits Panel ScreenBranch Ckt Loading Top right distribution panel Panel ConfigurationCircuit breakers occupying positions 08, 10, and 12 on Global Panel Config Config Screen System PasswordBeeper Volume Select High , Medium , Low , or Off to adjust Date/TimeElectrical Config Input ConfigOutput Config Manufacturer DataSystem ID Factory DefaultsFirmware Updates How to Apply Power to the System OperationOperation How to Apply Power to the System How to Ensure Total Power Off Page InfraStruXure PDU Management Options OverviewInfraStruXure Manager Network management interfacesConfiguring the InfraStruXure Manager Connect the InfraStruXure PDU to the InfraStruXure ManagerConnect the InfraStruXure PDU to your network Configuring the Network Management InterfaceConfiguration Overview TCP/IP configuration methods Device IP Configuration WizardBootp & Dhcp configuration Option 43 = 01 04 31 41 50 43 where 150kW InfraStruXure PDU-Operation and Configuration Remote access to the control console Local access to the control consoleUse apc for the User Name and Password Choose Network from the Control Console menu Use apc for both User Name and PasswordControl console Web interface Snmp FTP and SCP 150kW InfraStruXure PDU-Operation and Configuration Page Important Safety Instructions Customizing and Updating the PDUPDU Orderable Part List BreakersCustomizing and Updating the PDU Add a circuit breaker on the PDU How to Add Circuit Breakers and Power CablesAdd a power cable to the PDU Customizing and Updating the PDU Overview How to attach the circuit breaker to the mounting brackets How to connect the sub-feed cable to the circuit breaker ATS 0 ATS 1 ATS Atsen How to connect contacts to the PDU monitoring unit How to Connect an EPO Switch to the PDU and Test the Switch Contact closure 24VAC 24VDC Contact closure is recommended24VAC/VDC-Normally Open Contact Closure-Normally OpenContact Closure-Normally Closed Problem Action Safety warnings How to Download Firmware Updates From a local computerPage Specifications 150kW InfraStruXure PDUPhysical PD150G6F PD150L6F Warranty InfraStruXure Standard WarrantyProduct Information Warranty APC Three-Phase Systems Life-Support PolicyHow to Obtain Service How to contact APCIndex SSH Page Page Page 990-1984