Load-Meter Screen

From the Load-Meterscreen, you can select the following items:

Total Load by Phase The load supported by each phase in kilovolt-amperes (kVA), in RMS current (Irms), and as a percentage of the maximum allowable load (%LD).

Total Load Summary For the total load supported:

 

kW: The power provided, in kilowatts.

 

kVA: The actual power drawn by the load, in kilovolt-amperes.

 

Freq: The frequency.

 

PF: The power factor, which affects the power available to the

 

 

load.

 

%LD: The load as a percentage of the maximum allowable

 

 

load.

Power Factor

For each phase:

 

kVA: The actual power drawn by the load, in kilovolt-amperes.

 

kW: The power, in kilowatts, provided by the phase.

 

PF: The power factor (kW/kVA) that affects the power

 

 

available to the load.

16

150kW InfraStruXure PDU—Operation and Configuration

Image 24
Contents 150kW InfraStruXure PDU Page About this Manual Page Contents Operation Customizing and Updating the PDU Product Information Safety symbols used in this manual Cross-reference symbols used in this manualOverview Installation/maintenance Receiving/movingTotal power off procedure Emergency Power Off EPOEMI Overview InfraStruXure PDU ComponentsInfraStruXure PDU Front viewFront view interior Rear view Rear view interior PDU monitoring unit Left = 43..83 lower right = User connection plate PDU Display Interface Top-level status screens Top-level menu screenNavigating through screens Password-protected screens Power Factor Load-Meter ScreenVolt-Meter Screen Contacts Screen Input ContactsOpen or Closed Relay OutputsAlarm Relay Map How to connect contacts to the PDU monitoring unit Breakers Screen Main InputAlarms Screen New Logged ItemsEntire Log Clear LogGlobal Alarm ConfigLoading Limits Voltage LimitsPDU Alarms Alarm Condition ExplanationPanel Screen Branch Ckt LoadingBranch Ckt Limits Panel Configuration Circuit breakers occupying positions 08, 10, and 12 onTop right distribution panel Global Panel Config Config Screen System PasswordBeeper Volume Select High , Medium , Low , or Off to adjust Date/TimeElectrical Config Input ConfigOutput Config Manufacturer DataFactory Defaults Firmware UpdatesSystem ID How to Apply Power to the System OperationOperation How to Apply Power to the System How to Ensure Total Power Off Page InfraStruXure PDU Management Options OverviewInfraStruXure Manager Network management interfacesConfiguring the InfraStruXure Manager Connect the InfraStruXure PDU to the InfraStruXure ManagerConfiguring the Network Management Interface Configuration OverviewConnect the InfraStruXure PDU to your network TCP/IP configuration methods Device IP Configuration WizardBootp & Dhcp configuration Option 43 = 01 04 31 41 50 43 where 150kW InfraStruXure PDU-Operation and Configuration Local access to the control console Use apc for the User Name and PasswordRemote access to the control console Use apc for both User Name and Password Control consoleChoose Network from the Control Console menu Web interface Snmp FTP and SCP 150kW InfraStruXure PDU-Operation and Configuration Page Important Safety Instructions Customizing and Updating the PDUPDU Orderable Part List BreakersCustomizing and Updating the PDU How to Add Circuit Breakers and Power Cables Add a power cable to the PDUAdd a circuit breaker on the PDU Customizing and Updating the PDU Overview How to attach the circuit breaker to the mounting brackets How to connect the sub-feed cable to the circuit breaker ATS 0 ATS 1 ATS Atsen How to connect contacts to the PDU monitoring unit How to Connect an EPO Switch to the PDU and Test the Switch Contact closure 24VAC 24VDC Contact closure is recommendedContact Closure-Normally Open Contact Closure-Normally Closed24VAC/VDC-Normally Open Problem Action Safety warnings How to Download Firmware Updates From a local computerPage Specifications 150kW InfraStruXure PDUPhysical PD150G6F PD150L6F Warranty InfraStruXure Standard WarrantyProduct Information Warranty APC Three-Phase Systems Life-Support PolicyHow to Obtain Service How to contact APCIndex SSH Page Page Page 990-1984