American Power Conversion PD150G6F How to attach the circuit breaker to the mounting brackets

Page 63

Customizing and Updating the PDU

How to attach the circuit breaker to the mounting brackets

1. Mount the circuit breaker according to the instructions provided by the manufacturer.

Install a plastic insulating piece behind the circuit breaker before mounting it.

Note

2.Remove the blanking plate from the door of the PDU and replace it with the faceplate supplied with the sub-feed breaker kit.

3.Using the provided hardware, fasten the L3 cable to the top of the sub-feed circuit breaker you are installing, according to the following illustration. Torque to 70in-lb (8Nm).

4.Insert the remaining (stripped) end of the L3 cable into the L3 lug of the terminal block inside the PDU. Torque to 275in-lb (32Nm). The following illustrations show the location of the terminal block inside the PDU and the point on the terminal block where the connection is made.

5. Repeat step 3 and step 4 for the remaining L2 and L1 cables.

150kW InfraStruXure PDU—Operation and Configuration

55

Image 63
Contents 150kW InfraStruXure PDU Page About this Manual Page Contents Operation Customizing and Updating the PDU Product Information Safety symbols used in this manual Cross-reference symbols used in this manualOverview Receiving/moving Installation/maintenanceEmergency Power Off EPO Total power off procedureEMI InfraStruXure PDU Components OverviewFront view InfraStruXure PDUFront view interior Rear view Rear view interior PDU monitoring unit Left = 43..83 lower right = User connection plate PDU Display Interface Top-level status screens Top-level menu screenNavigating through screens Password-protected screens Load-Meter Screen Power FactorVolt-Meter Screen Relay Outputs Contacts ScreenInput Contacts Open or ClosedAlarm Relay Map How to connect contacts to the PDU monitoring unit Main Input Breakers ScreenClear Log Alarms ScreenNew Logged Items Entire LogVoltage Limits Global AlarmConfig Loading LimitsAlarm Condition Explanation PDU AlarmsPanel Screen Branch Ckt LoadingBranch Ckt Limits Panel Configuration Circuit breakers occupying positions 08, 10, and 12 onTop right distribution panel Global Panel Config Date/Time Config ScreenSystem Password Beeper Volume Select High , Medium , Low , or Off to adjustManufacturer Data Electrical ConfigInput Config Output ConfigFactory Defaults Firmware UpdatesSystem ID Operation How to Apply Power to the SystemOperation How to Apply Power to the System How to Ensure Total Power Off Page Network management interfaces InfraStruXure PDU Management OptionsOverview InfraStruXure ManagerConnect the InfraStruXure PDU to the InfraStruXure Manager Configuring the InfraStruXure ManagerConfiguring the Network Management Interface Configuration OverviewConnect the InfraStruXure PDU to your network Device IP Configuration Wizard TCP/IP configuration methodsBootp & Dhcp configuration Option 43 = 01 04 31 41 50 43 where 150kW InfraStruXure PDU-Operation and Configuration Local access to the control console Use apc for the User Name and PasswordRemote access to the control console Use apc for both User Name and Password Control consoleChoose Network from the Control Console menu Web interface Snmp FTP and SCP 150kW InfraStruXure PDU-Operation and Configuration Page Customizing and Updating the PDU Important Safety InstructionsBreakers PDU Orderable Part ListCustomizing and Updating the PDU How to Add Circuit Breakers and Power Cables Add a power cable to the PDUAdd a circuit breaker on the PDU Customizing and Updating the PDU Overview How to attach the circuit breaker to the mounting brackets How to connect the sub-feed cable to the circuit breaker ATS 0 ATS 1 ATS Atsen How to connect contacts to the PDU monitoring unit Contact closure 24VAC 24VDC Contact closure is recommended How to Connect an EPO Switch to the PDU and Test the SwitchContact Closure-Normally Open Contact Closure-Normally Closed24VAC/VDC-Normally Open Problem Action Safety warnings From a local computer How to Download Firmware UpdatesPage 150kW InfraStruXure PDU SpecificationsPhysical PD150G6F PD150L6F InfraStruXure Standard Warranty WarrantyProduct Information Warranty Life-Support Policy APC Three-Phase SystemsHow to contact APC How to Obtain ServiceIndex SSH Page Page Page 990-1984