PDU Display Interface: Config Screen

Electrical Config

This option of the Config screen displays information about the electrical service that provides input to the InfraStruXure PDU. All of the values displayed on this screen are set at the factory. Use this information when viewing and setting alarms.

Input Config

Configure the following items:

 

Main Input: The voltage from the power source coming into

 

 

the PDU main input switch.

 

 

• 3W: 3-phase Delta, measured line-to-line

 

 

• 4W: 3-phase WYE, measured line-to-neutral

 

Transformer: Indicates whether the InfraStruXure PDU has

 

 

a transformer.

Output Config

Configure the following items:

 

Panel Voltage: The nominal voltage of the distribution panels

 

 

supplying power to the load equipment. (This is measured

 

 

line-to-neutral.)

 

Panel Breaker: The rating, in amps, of the circuit breaker

 

 

feeding the distribution panels.

Manufacturer Data

Use this option of the Config screen to display a scrollable list containing information about the InfraStruXure PDU. This information is useful when requesting service or product updates. The following information is displayed:

Manufacturer Name

Date of Manufacture

Date of Calibration

Hardware Revision

Firmware Revision (for PDU Monitoring and Metering)

Serial Number

Model Number

150kW InfraStruXure PDU—Operation and Configuration

29

Image 37
Contents 150kW InfraStruXure PDU Page About this Manual Page Contents Operation Customizing and Updating the PDU Product Information Cross-reference symbols used in this manual Safety symbols used in this manualOverview Receiving/moving Installation/maintenanceEmergency Power Off EPO Total power off procedureEMI InfraStruXure PDU Components OverviewFront view InfraStruXure PDUFront view interior Rear view Rear view interior PDU monitoring unit Left = 43..83 lower right = User connection plate PDU Display Interface Top-level menu screen Top-level status screensNavigating through screens Password-protected screens Load-Meter Screen Power FactorVolt-Meter Screen Input Contacts Contacts ScreenOpen or Closed Relay OutputsAlarm Relay Map How to connect contacts to the PDU monitoring unit Main Input Breakers ScreenNew Logged Items Alarms ScreenEntire Log Clear LogConfig Global AlarmLoading Limits Voltage LimitsAlarm Condition Explanation PDU AlarmsBranch Ckt Loading Panel ScreenBranch Ckt Limits Circuit breakers occupying positions 08, 10, and 12 on Panel ConfigurationTop right distribution panel Global Panel Config System Password Config ScreenBeeper Volume Select High , Medium , Low , or Off to adjust Date/TimeInput Config Electrical ConfigOutput Config Manufacturer DataFirmware Updates Factory DefaultsSystem ID Operation How to Apply Power to the SystemOperation How to Apply Power to the System How to Ensure Total Power Off Page Overview InfraStruXure PDU Management OptionsInfraStruXure Manager Network management interfacesConnect the InfraStruXure PDU to the InfraStruXure Manager Configuring the InfraStruXure ManagerConfiguration Overview Configuring the Network Management InterfaceConnect the InfraStruXure PDU to your network Device IP Configuration Wizard TCP/IP configuration methodsBootp & Dhcp configuration Option 43 = 01 04 31 41 50 43 where 150kW InfraStruXure PDU-Operation and Configuration Use apc for the User Name and Password Local access to the control consoleRemote access to the control console Control console Use apc for both User Name and PasswordChoose Network from the Control Console menu Web interface Snmp FTP and SCP 150kW InfraStruXure PDU-Operation and Configuration Page Customizing and Updating the PDU Important Safety InstructionsBreakers PDU Orderable Part ListCustomizing and Updating the PDU Add a power cable to the PDU How to Add Circuit Breakers and Power CablesAdd a circuit breaker on the PDU Customizing and Updating the PDU Overview How to attach the circuit breaker to the mounting brackets How to connect the sub-feed cable to the circuit breaker ATS 0 ATS 1 ATS Atsen How to connect contacts to the PDU monitoring unit Contact closure 24VAC 24VDC Contact closure is recommended How to Connect an EPO Switch to the PDU and Test the SwitchContact Closure-Normally Closed Contact Closure-Normally Open24VAC/VDC-Normally Open Problem Action Safety warnings From a local computer How to Download Firmware UpdatesPage 150kW InfraStruXure PDU SpecificationsPhysical PD150G6F PD150L6F InfraStruXure Standard Warranty WarrantyProduct Information Warranty Life-Support Policy APC Three-Phase SystemsHow to contact APC How to Obtain ServiceIndex SSH Page Page Page 990-1984