American Power Conversion PD150G6F, PD150L6F manual

Page 81
Image 81
Contents 150kW InfraStruXure PDU Page About this Manual Page Contents Operation Customizing and Updating the PDU Product Information Safety symbols used in this manual Cross-reference symbols used in this manualOverview Receiving/moving Installation/maintenanceEmergency Power Off EPO Total power off procedureEMI InfraStruXure PDU Components OverviewFront view InfraStruXure PDUFront view interior Rear view Rear view interior PDU monitoring unit Left = 43..83 lower right = User connection plate PDU Display Interface Top-level status screens Top-level menu screenNavigating through screens Password-protected screens Load-Meter Screen Power FactorVolt-Meter Screen Input Contacts Contacts ScreenOpen or Closed Relay OutputsAlarm Relay Map How to connect contacts to the PDU monitoring unit Main Input Breakers ScreenNew Logged Items Alarms ScreenEntire Log Clear LogConfig Global AlarmLoading Limits Voltage LimitsAlarm Condition Explanation PDU AlarmsPanel Screen Branch Ckt LoadingBranch Ckt Limits Panel Configuration Circuit breakers occupying positions 08, 10, and 12 onTop right distribution panel Global Panel Config System Password Config ScreenBeeper Volume Select High , Medium , Low , or Off to adjust Date/TimeInput Config Electrical ConfigOutput Config Manufacturer DataFactory Defaults Firmware UpdatesSystem ID Operation How to Apply Power to the SystemOperation How to Apply Power to the System How to Ensure Total Power Off Page Overview InfraStruXure PDU Management OptionsInfraStruXure Manager Network management interfacesConnect the InfraStruXure PDU to the InfraStruXure Manager Configuring the InfraStruXure ManagerConfiguring the Network Management Interface Configuration OverviewConnect the InfraStruXure PDU to your network Device IP Configuration Wizard TCP/IP configuration methodsBootp & Dhcp configuration Option 43 = 01 04 31 41 50 43 where 150kW InfraStruXure PDU-Operation and Configuration Local access to the control console Use apc for the User Name and PasswordRemote access to the control console Use apc for both User Name and Password Control consoleChoose Network from the Control Console menu Web interface Snmp FTP and SCP 150kW InfraStruXure PDU-Operation and Configuration Page Customizing and Updating the PDU Important Safety InstructionsBreakers PDU Orderable Part ListCustomizing and Updating the PDU How to Add Circuit Breakers and Power Cables Add a power cable to the PDUAdd a circuit breaker on the PDU Customizing and Updating the PDU Overview How to attach the circuit breaker to the mounting brackets How to connect the sub-feed cable to the circuit breaker ATS 0 ATS 1 ATS Atsen How to connect contacts to the PDU monitoring unit Contact closure 24VAC 24VDC Contact closure is recommended How to Connect an EPO Switch to the PDU and Test the SwitchContact Closure-Normally Open Contact Closure-Normally Closed24VAC/VDC-Normally Open Problem Action Safety warnings From a local computer How to Download Firmware UpdatesPage 150kW InfraStruXure PDU SpecificationsPhysical PD150G6F PD150L6F InfraStruXure Standard Warranty WarrantyProduct Information Warranty Life-Support Policy APC Three-Phase SystemsHow to contact APC How to Obtain ServiceIndex SSH Page Page Page 990-1984