APC 6000 installation manual Handling, Positioning the cubicles, Front, Cubicle

Page 10

Installation

(to be carried out by qualified personnel only)

Handling

Unpacked cubicles may be moved using a forklift from the front or from the back. Distances must not exceed a few meters.

Positioning the cubicles

(for 600 kVA UPSs, see the appendix as well)

prior to moving the cubicles to their final position, remove the packing material and withdraw the base panels from the space on the side created by the spacing uprights. The panels will be installed at the end of the installation procedure;

spacing uprights on the sides of the cubicles create a 50 mm clearance when cubicles are positioned next to each other, enabling users to open the doors (see figure 4). If a cubicle is installed next to a wall, leave additional space so that the cubicle is 50 mm from the wall;

when the spacing uprights are not required (cubicles are not positioned next to a wall or another cubicle), they may be removed:

loosen the four screws securing the upright,

lift the upright and pull it free,

replace the long gold-coloured screws with the black screws supplied in a bag attached to the cable terminals in the cubicle;

adjust the height of the feet until the first cubicle is perfectly vertical; adjust the feet of the subsequent cubicles so that the all the doors are perfectly aligned.

Side clearances provided by the spacing uprights

rear

 

 

 

50

50

 

cubicle 1

cubicle 2

front

spacing uprights

spacing uprights

of cubicle 1

of cubicle 2

Fig. 4

Page 10 - 6739381EN/JD

Image 10
Contents Mgetm GalaxyTM 2 6739381EN/JD Contents Characteristics Characteristics common to all cubiclesRectifier-inverter cubicles Static Switch cubiclesExternal maintenance bypass cubicles Pack Advance cubiclesRemark Electrical parameters for selecting protective devicesElectrical parameters for Mains Electrical parameters for Mains 2 Electrical parameters for determining cable cross-sections Heat lossesNumber Total UPS Installation with parallel frequency convertersInstallation with parallel UPSs with a centralised SSC Line current Mm2 KVA Inverters Amps Copper AluminiumLine current Number Total UPS Mains 2 or loadKVA Inverters Amps Copper Side clearances provided by the spacing uprights Rear HandlingPositioning the cubicles FrontCubicle layout on false floor or normal floor figures 6, 7 Layout for a single-unit UPS with one battery cubicleFloor loads figure Cubicle footpads RearSpecial case Power circuit wiring diagramsConnection via the top Rectifier-inverter cubicleStatic Switch Cubicle Diagram for a frequency converter with batteriesDiagram for a frequency converter without batteries Example of a 2 parallel UPS rectifier-inverters with SSCModular UPS cubicle External maintenance bypass cubicle General Connection of power circuitsCross-section AA 160kVA to 400kVA modular UPS rectifier-inverter cubicle KVA single-unit UPS cubicles see the appendixXR2 XR5 XR3 XR6 Acpz XR4 XR7 600kVA parallel UPS cubicles see the appendixApoz Off 500kVA single-unit UPS rectifier-inverter cubicle600kVA single-unit UPS cubicles see the appendix XR4 XR7XM7 XR2 XR5 500kVA modular UPS rectifier-inverter cubicleXR4 XR7 XM5 XR1 XR8 Air admission Mains 1, load BatteryL1L2 L3 L1 L2 L3 Mains Battery Load XM133 Q1onXR9 XR2 Q4S 500/800kVA Static Switch CubicleFront Rear XR3 XR4 XR7XR7 XR4 UPS XR6 1200kVA Static Switch CubicleFront view XR3 XR5 XR2 XR9 XR1 XR8Terminal Important noteAuxiliary Block XR11200kVA external maintenance bypass cubicle Key to figureConnection of auxiliary circuits on the remote relay board XR1 XR2 XR3 XR4Emergency shutdown Connection to battery circuit breaker QF1Connections between cubicles Connections between Apoz boards127 128 129 130 131 Connections between Misi boards modular UPSsXM XM XM XM XM XM MisiMisi Acpz board of the Static Switch Cubicle XR8 XR9 XR5 XR6 XR7Connection of the battery Temperature Monitor optional ConnectionsTemperature Monitor installation in a battery room Temperature Monitor installation in a APC bySchneider Electric battery cubicle Installing the Temperature Monitor in a battery cubicleLink to an IBM AS/400→ computer Rauz 1 board XM098 XM097 XR11 XM096 XR10 Connector XR10Connection of the LED remote indications unit Consult manual 6739388XU for further informationConnection to the Media Contacts 9 relay board Final installation stepsConfiguration of the AS/400→ After making the connectionsUPS 250 to 450kVA Mains 2 line protectionRated inverter output Maximum permissible current KVA UPS 500kVACubicle mounting Cubicle mounting and connection for 600kVA UPSsInternal connections between cubicles Connection of power and auxiliary circuits Left cubicle of 600kVA single-unit or parallel UPS with SSCXR2 XR5 XR3 XR6 XR4 XR7 Right cubicle of a 600kVA single-unit UPSMains Load L1 L2 L3 Air Admission Air admission Load Right cubicle of a 600kVA parallel UPS with SSCXR3 XR6 XR4 Q3BP XF1-XF2 XM1-XM2 Left cubicleRight cubicle Card cageAir admission Air extraction Right cubicle of a 2000kVA Static SwitchCross-section AA Front view Mains OffXR6 XR3 XR5 XR2 Left cubicle of a 2000kVA Static SwitchXR9 XR1 XR8 450 500kVA rectifier-inverter cubicle Details of earthing connections in the various cubicles250 to 400kVA rectifier-inverter cubicle Inverter input600kVA rectifier-inverter cubicle 120 to 1200kVA Static Switch CubiclesInverter Input Connection with Bolt, nut andmains 2 contact washer 2000kVA Static Switch CubiclesTele-Monitor unit Tele Monitor unit6739381ENPage 46 --JD6739381EN/JD
Related manuals
Manual 38 pages 11.72 Kb