Installation (cont.)

Connection to battery circuit breaker QF1

Connect the cable from connector XR3 (pins 7 to 12) of the rectifier-inverter cubicle remote relay board to connector XR1 of the battery cubicle containing battery circuit breaker QF1.

Emergency shutdown

The UPS emergency shutdown function is generally wired to a "mushroom-head" type emergency off button.

Important:

In the case of a complex installation with a number of units, there should only be one emergency shutdown pushbutton and this pushbutton must interrupt all the active conductors of all the units.

For the same reason, it is essential for the pushbutton to open the upstream mains 1, mains 2, and external maintenance bypass line protective

circuit breakers.

Each type of unit (UPS and Static Switch Cubicle) must have an independent, volt-free contact connected to the emergency shutdown pushbutton. This pushbutton must therefore have as many contacts as there are units in the installation, as well as the contact or contacts required to open the upstream mains 1 and 2 protective circuit breakers. The emergency shutdown pushbutton turns off the rectifier-chargers and inverters and opens the battery circuit breakers. The emergency shutdown signal will be cleared when the emergency shutdown

pushbutton contact has been reset. The emergency shutdown pushbutton should not be connected to the Static Switch Cubicle since the pushbutton opens the circuit breaker protecting the upstream circuit (mains 2) and the Static Switch Cubicle is therefore no longer powered (inverters off and mains 2 down).

Connections between cubicles

(modular UPSs or parallel UPSs with SSC)

On modular UPSs, interconnections are made on the APOZ (figure 17) and MISI (figures 19 to 21) boards in the UPS cubicles (see the layout of the boards in the figures in the previous section).

For parallel UPSs with a centralised SSC, interconnections are made on the APOZ boards in the UPS cubicles (figure 17) and the ACPZ boards (see the layout of the boards in the figures in the previous section) in the SSC (figure 18).

Connections between APOZ boards

these connections are made using the ribbon cables supplied;

the purpose of the connection is to make a loop: connector XM137 of the APOZ board of one UPS being connected to connector XM136 of the APOZ board of the next UPS and so on until the first board is returned to.

Important:

Outside the cubicles, group the APOZ inter-board and ACPZ or MISI inter- board connections with the inter-cubicle auxiliary connections, and separate this assembly from the power cables.

Connections between rectifier-inverter cubicles

APOZ board rectifier-inverter 1

XM137

XM136

APOZ board rectifier-inverter 2

ribbon cables supplied

XM137

XM136

APOZ board rectifier-inverter 3

XM137

XM136

Fig. 17

6739381EN/

Image 27
Contents Mgetm GalaxyTM 2 6739381EN/JD Contents Characteristics common to all cubicles CharacteristicsPack Advance cubicles Static Switch cubiclesExternal maintenance bypass cubicles Rectifier-inverter cubiclesElectrical parameters for Mains 2 Electrical parameters for selecting protective devicesElectrical parameters for Mains RemarkHeat losses Electrical parameters for determining cable cross-sectionsLine current Mm2 KVA Inverters Amps Copper Aluminium Installation with parallel frequency convertersInstallation with parallel UPSs with a centralised SSC Number Total UPSNumber Total UPS Mains 2 or load Line currentKVA Inverters Amps Copper Front HandlingPositioning the cubicles Side clearances provided by the spacing uprights RearCubicle footpads Rear Layout for a single-unit UPS with one battery cubicleFloor loads figure Cubicle layout on false floor or normal floor figures 6, 7Rectifier-inverter cubicle Power circuit wiring diagramsConnection via the top Special caseExample of a 2 parallel UPS rectifier-inverters with SSC Diagram for a frequency converter with batteriesDiagram for a frequency converter without batteries Static Switch CubicleModular UPS cubicle External maintenance bypass cubicle Connection of power circuits GeneralCross-section AA KVA single-unit UPS cubicles see the appendix 160kVA to 400kVA modular UPS rectifier-inverter cubicle600kVA parallel UPS cubicles see the appendix XR2 XR5 XR3 XR6 Acpz XR4 XR7Apoz XR4 XR7 500kVA single-unit UPS rectifier-inverter cubicle600kVA single-unit UPS cubicles see the appendix Off500kVA modular UPS rectifier-inverter cubicle XM7 XR2 XR5XR4 XR7 XM5 XM133 Q1on Air admission Mains 1, load BatteryL1L2 L3 L1 L2 L3 Mains Battery Load XR1 XR8XR3 XR4 XR7 500/800kVA Static Switch CubicleFront Rear XR9 XR2 Q4SXR3 XR5 XR2 XR9 XR1 XR8 1200kVA Static Switch CubicleFront view XR7 XR4 UPS XR6 Block XR1 Important note Auxiliary TerminalKey to figure 1200kVA external maintenance bypass cubicleXR1 XR2 XR3 XR4 Connection of auxiliary circuits on the remote relay boardConnections between Apoz boards Connection to battery circuit breaker QF1Connections between cubicles Emergency shutdownMisi Connections between Misi boards modular UPSsXM XM XM XM XM XM 127 128 129 130 131Misi XR8 XR9 XR5 XR6 XR7 Acpz board of the Static Switch CubicleConnections Connection of the battery Temperature Monitor optionalInstalling the Temperature Monitor in a battery cubicle Temperature Monitor installation in a APC bySchneider Electric battery cubicle Temperature Monitor installation in a battery roomConsult manual 6739388XU for further information Rauz 1 board XM098 XM097 XR11 XM096 XR10 Connector XR10Connection of the LED remote indications unit Link to an IBM AS/400→ computerAfter making the connections Final installation stepsConfiguration of the AS/400→ Connection to the Media Contacts 9 relay boardUPS 500kVA Mains 2 line protectionRated inverter output Maximum permissible current KVA UPS 250 to 450kVACubicle mounting and connection for 600kVA UPSs Cubicle mountingInternal connections between cubicles Left cubicle of 600kVA single-unit or parallel UPS with SSC Connection of power and auxiliary circuitsRight cubicle of a 600kVA single-unit UPS XR2 XR5 XR3 XR6 XR4 XR7Mains Load L1 L2 L3 Air Admission Right cubicle of a 600kVA parallel UPS with SSC Air admission LoadXR3 XR6 XR4 Card cage Left cubicleRight cubicle Q3BP XF1-XF2 XM1-XM2Mains Off Right cubicle of a 2000kVA Static SwitchCross-section AA Front view Air admission Air extractionLeft cubicle of a 2000kVA Static Switch XR6 XR3 XR5 XR2XR9 XR1 XR8 Inverter input Details of earthing connections in the various cubicles250 to 400kVA rectifier-inverter cubicle 450 500kVA rectifier-inverter cubicle120 to 1200kVA Static Switch Cubicles 600kVA rectifier-inverter cubicleInverter Input Tele Monitor unit 2000kVA Static Switch CubiclesTele-Monitor unit Connection with Bolt, nut andmains 2 contact washer6739381ENPage 46 --JD6739381EN/JD