Gusset plates have been fitted to the top corners on all four sides of the cubicles to provide reinforcement for transportation.

prior to joining the two cubicles, remove the two gussets from the right side of the left cubicle;

move the cubicles to their operating location;

adjust the front foot pads so that the cubicles are vertical and their doors aligned;

remove the top panel on the left side of the right cubicle for access to the side gussets (see figure opposite);

remove the gussets 1 on the front of the left cubicle;

remove and turn around the double gussets 2 on the right cubicle and use them to bolt the two cubicles together.

left cubicle

1

single gusset

to be

removed

right cubicle

A

B

 

2

 

double gusset

 

to be

 

turned around

Internal connections between cubicles

removal of inverter leg no.6 is recommended prior to bolting fish- plates L+ and L–:

first remove the two fuses and the two cables connected to the leg,

then pull the leg out;

bolt fish-plates L+ and L–;

refit inverter leg no 6;

intended only for transportation, the front gussets do not need to be refitted;

bolt cables L1, L2, L3 and N (4 x 2) coming from the right cubicle to the terminals marked L1, L2, L3 and N respectively, in the left cubicle;

connect the earth strap to the front uprights of both cubicles;

connect the connectors marked XF281 to XF285 on the five ribbon cables coming from the left cubicle to connectors XM281 to XM285 respectively on the interface board located on the left side of the right cubicle;

connect the connectors marked XF01 to XF06 (XF01 to XF07 for parallel UPSs) on the control wires coming from the left cubicle to connectors XM01 to XM06 (XM01 to XM07 for parallel UPSs) on the plate on the left side of the right cubicle.

left cubicle

 

right cubicle

inverter leg no. 6

fuses and cables

 

to be disconnected

 

L

fish-plates

 

L+

to be

 

bolted

 

earthing connection

 

between cubicles

 

interface board

L3

and connection

plate for control

L2

wires

 

L1

 

 

 

N

 

 

cables to be

 

 

connected

 

 

Page 36 - 6739381EN/JD

Image 36
Contents Mgetm GalaxyTM 2 6739381EN/JD Contents Characteristics Characteristics common to all cubiclesStatic Switch cubicles External maintenance bypass cubiclesRectifier-inverter cubicles Pack Advance cubiclesElectrical parameters for selecting protective devices Electrical parameters for MainsRemark Electrical parameters for Mains 2Electrical parameters for determining cable cross-sections Heat lossesInstallation with parallel frequency converters Installation with parallel UPSs with a centralised SSCNumber Total UPS Line current Mm2 KVA Inverters Amps Copper AluminiumNumber Total UPS Mains 2 or load Line currentKVA Inverters Amps Copper Handling Positioning the cubiclesSide clearances provided by the spacing uprights Rear FrontLayout for a single-unit UPS with one battery cubicle Floor loads figureCubicle layout on false floor or normal floor figures 6, 7 Cubicle footpads RearPower circuit wiring diagrams Connection via the topSpecial case Rectifier-inverter cubicleDiagram for a frequency converter with batteries Diagram for a frequency converter without batteriesStatic Switch Cubicle Example of a 2 parallel UPS rectifier-inverters with SSCModular UPS cubicle External maintenance bypass cubicle Connection of power circuits GeneralCross-section AA 160kVA to 400kVA modular UPS rectifier-inverter cubicle KVA single-unit UPS cubicles see the appendix600kVA parallel UPS cubicles see the appendix XR2 XR5 XR3 XR6 Acpz XR4 XR7Apoz 500kVA single-unit UPS rectifier-inverter cubicle 600kVA single-unit UPS cubicles see the appendixOff XR4 XR7500kVA modular UPS rectifier-inverter cubicle XM7 XR2 XR5XR4 XR7 XM5 Air admission Mains 1, load Battery L1L2 L3 L1 L2 L3 Mains Battery LoadXR1 XR8 XM133 Q1on500/800kVA Static Switch Cubicle Front RearXR9 XR2 Q4S XR3 XR4 XR71200kVA Static Switch Cubicle Front viewXR7 XR4 UPS XR6 XR3 XR5 XR2 XR9 XR1 XR8Important note AuxiliaryTerminal Block XR11200kVA external maintenance bypass cubicle Key to figureConnection of auxiliary circuits on the remote relay board XR1 XR2 XR3 XR4Connection to battery circuit breaker QF1 Connections between cubiclesEmergency shutdown Connections between Apoz boardsConnections between Misi boards modular UPSs XM XM XM XM XM XM127 128 129 130 131 MisiMisi Acpz board of the Static Switch Cubicle XR8 XR9 XR5 XR6 XR7Connection of the battery Temperature Monitor optional ConnectionsTemperature Monitor installation in a APC by Schneider Electric battery cubicleTemperature Monitor installation in a battery room Installing the Temperature Monitor in a battery cubicle Rauz 1 board XM098 XM097 XR11 XM096 XR10 Connector XR10 Connection of the LED remote indications unit Link to an IBM AS/400→ computer Consult manual 6739388XU for further informationFinal installation steps Configuration of the AS/400→Connection to the Media Contacts 9 relay board After making the connectionsMains 2 line protection Rated inverter output Maximum permissible current KVAUPS 250 to 450kVA UPS 500kVACubicle mounting and connection for 600kVA UPSs Cubicle mountingInternal connections between cubicles Connection of power and auxiliary circuits Left cubicle of 600kVA single-unit or parallel UPS with SSCRight cubicle of a 600kVA single-unit UPS XR2 XR5 XR3 XR6 XR4 XR7Mains Load L1 L2 L3 Air Admission Right cubicle of a 600kVA parallel UPS with SSC Air admission LoadXR3 XR6 XR4 Left cubicle Right cubicleQ3BP XF1-XF2 XM1-XM2 Card cageRight cubicle of a 2000kVA Static Switch Cross-section AA Front viewAir admission Air extraction Mains OffLeft cubicle of a 2000kVA Static Switch XR6 XR3 XR5 XR2XR9 XR1 XR8 Details of earthing connections in the various cubicles 250 to 400kVA rectifier-inverter cubicle450 500kVA rectifier-inverter cubicle Inverter input120 to 1200kVA Static Switch Cubicles 600kVA rectifier-inverter cubicleInverter Input 2000kVA Static Switch Cubicles Tele-Monitor unitConnection with Bolt, nut andmains 2 contact washer Tele Monitor unit6739381ENPage 46 --JD6739381EN/JD
Related manuals
Manual 38 pages 11.72 Kb