4
Installing the new level sensing cable
1Locate the new level sensing cable supplied with the Z-arm.
2Pass the transfer tubing through the open end of an LLD cable casing nearest the right-angle connector. The tubing should exit the back of the LLD cable casing approximately 6.5 cm from the end.
3Connect the transfer tubing to the top of the isolation probe holder using a 1/4"-28 nut and ferrule supplied with the tubing. Firmly tighten this fitting using the supplied headless nut extender (part number 49041032) since it holds the probe in place.
4Plug the right-angle connector on one end of the cable into socket one on the back of the Z-arm.
5Pass the cable through the LLD cable guide.
6Attach the split-tongue connector to the small hexagonal nut on the probe holder. Tighten the nut until snug (approximately one turn after finger-tightening).