| 4.8 |
| Control outputs |
|
|
|
|
| ||
|
|
|
|
|
|
|
| ||||
Overview of control | Different control output signals are available depending on the configuration of |
| |||||||||
outputs | thermostat via DIP switches 4 & 5, and parameters P46 & P47. |
|
|
| |||||||
| Control output |
| Modulating |
|
|
| Modulating |
| |||
|
|
|
|
|
| ||||||
| Product No. |
|
| DC 0 … 10 V |
| on/off |
| PWM |
|
| |
|
|
|
|
|
|
|
|
|
|
| |
| RDG400 |
|
| Y10 |
| Y1 |
| Y1 |
| Y1/Y2 |
|
|
|
|
|
|
|
|
|
|
| (1 x / ) |
|
DC 0..10 V control signal
Synchronization
4.8.1Control output for air flow
The demand calculated by the PI control from the current room temperature and setpoint is provided to the valve actuator as a continuous DC 0...10 V signal via output Y10.
A
In
1.When the controller starts up, a closing signal (actuator running time + 150% = 2.5 x running time) is delivered to ensure the actuator will be fully closed and synchronized with the control algorithm.
2.Each time the controller calculates the position fully closed, the actuator’s running time is extended + 150% to ensure the right position of the actuator.
3.When the actuator has reached the position calculated by the controller, a waiting time of 30 seconds is observed in order to stabilize the outputs.
Note: opening synchronization is available for valve outputs only.
|
| 23 / 42 |
|
|
|
Siemens | RDG100, RDG100T, RDG110, RDG140, RDG160 Basic Documentation | CE1P3182en |
Building Technologies | Functions | 28 May 2009 |