Installation
Step 3 – Fit cables and sleeves
To maintain safety approvals insert only the following numbers of cables per clamp, with sleeves where applicable. This will ensure that cables are retained correctly in their clamps.
Feed the cables through the clamps as follows, depending on cable size:
1mm2 (18 AWG) – 2 cable pairs* per clamp:
"2 x 5mm sleeves
#10mm sleeve
* If only one cable pair is required then use a dummy pair with sleeves to make up the space.
4mm2 (12 AWG) – 1 or 2 cable pairs per clamp
Do not tighten the clamps at this stage.
Step 4 – Terminate cables
Terminate the negative load cable(s) at the
Terminate the positive load cable(s) at the (+) terminal block(s) of the DC outlet(s).
Tighten the terminal screws. Required torque: 0.4 – 0.6 Nm (3.5 – 5.3
Ensure that the polarity at the DC outlet(s) matches the power input polarity of your equipment. Connecting reverse polarity equipment power cables to the DC outlets of a power system might cause damage to your equipment. Such damage is not covered by our warranty.
Ensure that the correct cable sizes have been used (1mm2/18 AWG for 6 A outlets and 4mm2/12 AWG for 25 A outlets).
Step 5 – Arrange sleeves and tighten clamp screws
Arrange the sleeves so that they are all within 10mm (3/8”) of the terminals.
Tighten all cable clamp screws. Required torque: 1.5 – 2 Nm (13.2 – 17.7
Tighten the screws of any unused clamps to prevent access to the DC output terminations.
Procedure complete