Connecting the Battery Cables (if applicable)

Step 1 - Prepare cable clamp

Cut off the two inside posts of the battery cable clamp to enable the battery cables and sleeve to fit.

Step 2 – Strip cable and fit sleeve

Strip approximately 17mm (3/4”) of the insulation from the cable ends. We recommend fitting cable ferrules over the cable ends.

Feed both battery cables through the 16mm sleeve.

Step 3 – Terminate cable

Terminate the positive battery cable at the Battery (+) terminal block. Terminate the negative battery cable at the Battery (-) terminal block. Tighten the terminal screws. Required torque: 2.5 - 3 Nm (22.1 – 26.5 lb-in).

Ensure that the polarity at the battery terminal blocks matches the polarity of the external battery. Connecting a reverse polarity battery to a power system will cause damage to the rectifier modules. Such damage may not be covered by the warranty.

"

#

16mm battery cable sleeve.

Battery cable clamp with posts removed.

Step 4 – Arrange sleeve and clamp the battery cables

Arrange the cable sleeve so that it is within 10mm (3/8”) of the terminals. Tighten the cable clamp screws. Required torque: 1.5 – 2 Nm (13.2 – 17.7 lb-in).

Copyright © 2005-2006 Eaton Corporation. All Rights Reserved.

3-9

IPN 997-00012-41D December 2006

 

Image 29
Contents Data Power Solutions Installation Guide Copyright 2005-2006 Eaton Corporation All Rights Reserved About This Guide About This Guide For Further Information and Technical AssistanceTable of Contents Chapter Operations Table of ContentsTopic General DescriptionOverview General Description Data Power Solutions Product RangeAPS3-05X Rack-Mounted Versions Data Power Solutions Product RangeAPS3-06X Desktop Versions APS6-05X Rack-Mounted Versions Access Power Rectifiers SM45 Supervisory Module SM45 Supervisory ModuleLow Voltage Disconnect if applicable Pre-Installation AC Inputs Pre-InstallationBatteries if applicable DC Outputs Servicing Inspecting the Equipment and Reporting Damage Installation Installation Mounting the Power SystemRack Installation rack-mounted versions only Location and EnvironmentDC Installation Practices DC Installation PracticesConnecting the DC Load Cables APS3-05X and APS6-05X Rack-Mounted Versions Installation DC Load Cable SpecificationsFit load cable clamps Connecting the DC Load CablesFit cables and sleeves Installing the External Batteries if applicable Installing the External Batteries if applicableBattery Sizing Battery LocationBattery Fault Protection Connecting the Battery Cables if applicableBattery Cable Specifications Before You StartPrepare cable clamp Connecting the Battery Cables if applicableConnecting the Battery Temperature Sensor Cable Repeat for other battery cables if requiredMounting the Battery Temperature Sensor AC Supply Requirements Connecting the Power System to the AC SupplyAC Installation Commissioning Commissioning Inserting the Access Power RectifiersChecklist Pre-Power-Up CheckPre-Power-Up Check Configuring the Power System for Operation Applying AC PowerBefore you start, you need Configuring the Power System for OperationLVD Hotlink Click to …Page Applying DC Power to the Load SM45 Operations SM45 Operations About the SM45 Front PanelTo change the display contrast To disable the audible indicator when an alarm is activeAbout the SM45 Front Panel To exit a display mode To enter a display modeTo scroll within a display mode About Display ModesTo view system values Viewing System Values Main Display ModeViewing System Values Main Display Mode Rules for displaying alarms and system status Viewing Alarms and System Status Messages Status View ModeImportant note about Rect Comms Lost alarm To view and clear alarmsTo view and edit a configuration parameter Viewing and Editing Configuration ParametersViewing and Editing Configuration Parameters SM45 Operations Communications Direct Connection Ethernet Communications OptionsCommunications SM45 Ethernet Setup DCTools SetupDCTools Setup Properties Direct Connection EthernetParameter Configuration Guidelines Setting Up Snmp TrapsTo enter the sysObjectID of a power system using DCTools Entering the sysObjectID of a Power SystemEntering the sysObjectID of a Power System Synchronizing the SM45 Real-time Clock To synchronize the SM45 real-time clock using DCToolsMaintenance Problem Possible Cause/s Required Action TroubleshootingMaintenance Troubleshooting LED Config Error Removing a Rectifier Replacing a RectifierReplacing a Rectifier Pull out the rectifierInserting a Rectifier To check and replace AC input fuses Replacing AC Input FusesReplacing AC Input Fuses Replacing the SM45 Real-time Clock Battery Glossary of Alarms Multiple Rectifier Fail Glossary of AlarmsPartial AC Fail Rectifier Comms Lost Rectifier Fail Sensor Fail System OverloadControl Function Glossary Battery Current Limit BCLControl Function Glossary Low Volts DisconnectSystem AC Input SpecificationsSystem DC Output EnvironmentDimensions H, W, D SpecificationsWeight APR48 RectifiersEquipment Incident Report SG/03 ISS04 United States of America Worldwide SupportPage Page Page SM45 Front Panel Menu Structure Configuration Mode Edit Mode