Facility Analysis

Check the site to be sure pre-installation work has been completed correctly. This includes:

†Location chosen for the shelves is adequate.

†Rack (if rack mounted) is properly secured or backboard (if wall mounted) is properly prepared.

†Power is available.

†Wiring to Base Station locations has been pulled and correctly terminated.

†Phone lines for the handsets are installed and properly terminated.

†Telephone system administrator is on-site to program the existing telephone system.

†If the work has not been completed, the Polycom Field Service Engineer may leave the site and reschedule the installation when the items have been completed or corrected, or may assist in preparing the site.

Check Components

At the installation site, unpack the system carefully, verify that there is no shipping damage, and store in a safe place. As the field service engineer unpacks, he or she must confirm that contents are correct by comparing with the shipping documents.

Before beginning the system installation, begin charging a handset. The Battery Packs for the handsets are not charged when shipped. At least one fully charged handset is required to test the system.

PN: 1725-36122-001_M.doc

39

Image 39
Contents SpectraLink 6300 MCU Installation Patent Information About This Guide Polycom Model NumbersRelated Documents Icons and Conventions Customer SupportContents System Initialization Test System System InstallationInstall Base Stations Site Certification Installation FormsIndex53H Page Installation Overview Install Shelves and Interface Modules Installation Steps and ResponsibilitiesSpectraLink 6000 System Description SpectraLink 6000 System SpectraLink 6000 System Components Master Control UnitSpectraLink 6000 System topology Shelf 1 Primary Shelf Intershelf Junction Panel Interface Modules CPA, CPU, CPM, CPP, CPF316 ShelfSystem Controller CSC or CSO301, 306, Expansion Shelf CSC300, CSO300Intershelf Junction Panel JPI300 Base StationsCcSpectraLink 6000 System SpectraLink 6000 Wireless TelephonesSpectraLink OAI Gateway Operator’s ConsoleSite Preparation Required hardware Required Materials Provided by CustomerOperator’s Console PC System administratorUnion labor Prepare Location for ShelvesRack mounting Prepare rack or wallSpectraLink 6300 MCU Facility Preparation Wall mounting Prepare Power for Shelves Wire specificationsRun Cables to Base Station Locations Pull cable Terminate Cables at Base Station Locations Interface Type Prepare Demarc BlocksTwo-wire analog or digital interface Multiple power pairsFour-wire digital interface Install Demarc Blocks Program Telephone SystemAssign and program ports Site Preparation Telephone Ports Base Station Power Pairs Data Two-wire analog or digital demarc blockBase Station Power Pairs Data Four-wire digital demarc blockFour-wire Digital Connector B Connect demarc block 25-pair cable Page System Installation Facility AnalysisCheck Components SpectraLink 6300 MCU Facility Preparation Install Shelves Rack mountWall mount Connect Power to Shelves Install Intershelf Junction PanelRun conduit to shelf Connect wire to terminalsInstall Interface Modules Install CardsInstall Expansion Shelf Controllers CSC300 Do not install any card in slot 1 of expansion shelves Connect the Intershelf Junction Panel Connect Demarc Block RJ-21Cables to Interface Module Mount Base Stations on Dropped Tile Ceilings Install Base StationsMount Base Stations on Finished Ceilings Install Outdoor Base Stations Wire outdoor Base StationsMount and connect outdoor Base Stations Power Up and Check Diagnostics System Initialization Page Voice-test each Base Station Test SystemRun Listen Verify Diagnostic Site Certification Page Site Preparation Checklist Installation FormsSpectraLink 6300 MCU Facility Preparation Shelf Number Interface Module Base Station Location WorksheetShelf Interface Module Extension Assignments WorksheetCustomer Acceptance Form SpectraLink 6300 MCU Facility Preparation Important Safety Information Safety NoticesPage Index OAI