Install Base Stations

Install Outdoor Base Stations

Outdoor Base Stations (RCO400) are equipped with a protective enclosure, designed to be mounted to a wall or pole. After the enclosure is mounted, the Base Station is inserted in the enclosure and connected.

The customer’s wire contractor is responsible for wiring and mounting the outdoor Base Station enclosure. The contractor is responsible for supplying screws, brackets, and other appropriate hardware.

If the wiring between the MCS300 and the telephone system leaves the building, consult the telephone system manual, the NEC, and local codes for instructions on providing lightning and other over- current protection.

Wire outdoor Base Stations

If the wiring for a Base Station exits a building—whether to reach an outdoor Base Station location or to reach a Base Station in another building—it should be equipped with primary protection according to the NEC and/or local codes.

Wiring that exits the building must also be protected at both ends by a Quick Clip Fuse from Reliable Electric, part number RSCP-2. Insert the Quick Clip fuses in place of bridging clips on a 66 block for the non-internal Base Station circuits.

Mount and connect outdoor Base Stations

1.Mount the outdoor Base Station enclosure to a wall or pole. The enclosure should be attached at the highest point available that will provide central coverage for the outdoor area.

2.Insert the Base Station wire through the compression fitting and tighten the fitting.

3.Wire the Base Station connector the same way as the RJ-45 connectors for the indoor Base Stations.

4.Place the Base Station inside the enclosure with the part number label facing the back of the enclosure.

PN: 1725-36122-001_M.doc

51

Image 51
Contents SpectraLink 6300 MCU Installation Patent Information About This Guide Polycom Model NumbersRelated Documents Icons and Conventions Customer SupportContents System Initialization Test System System InstallationInstall Base Stations Site Certification Installation FormsIndex53H Page Installation Overview Install Shelves and Interface Modules Installation Steps and ResponsibilitiesSpectraLink 6000 System Description SpectraLink 6000 System SpectraLink 6000 System Components Master Control UnitSpectraLink 6000 System topology Shelf 1 Primary Shelf Intershelf Junction Panel Interface Modules CPA, CPU, CPM, CPP, CPF316 ShelfSystem Controller CSC or CSO301, 306, Expansion Shelf CSC300, CSO300Intershelf Junction Panel JPI300 Base StationsCcSpectraLink 6000 System SpectraLink 6000 Wireless TelephonesSpectraLink OAI Gateway Operator’s ConsoleSite Preparation Required hardware Required Materials Provided by CustomerOperator’s Console PC System administratorUnion labor Prepare Location for ShelvesRack mounting Prepare rack or wallSpectraLink 6300 MCU Facility Preparation Wall mounting Prepare Power for Shelves Wire specificationsRun Cables to Base Station Locations Pull cable Terminate Cables at Base Station Locations Interface Type Prepare Demarc BlocksTwo-wire analog or digital interface Multiple power pairsFour-wire digital interface Install Demarc Blocks Program Telephone SystemAssign and program ports Site Preparation Telephone Ports Base Station Power Pairs Data Two-wire analog or digital demarc blockBase Station Power Pairs Data Four-wire digital demarc blockFour-wire Digital Connector B Connect demarc block 25-pair cable Page System Installation Facility AnalysisCheck Components SpectraLink 6300 MCU Facility Preparation Install Shelves Rack mountWall mount Connect Power to Shelves Install Intershelf Junction PanelRun conduit to shelf Connect wire to terminalsInstall Interface Modules Install CardsInstall Expansion Shelf Controllers CSC300 Do not install any card in slot 1 of expansion shelves Connect the Intershelf Junction Panel Connect Demarc Block RJ-21Cables to Interface Module Mount Base Stations on Dropped Tile Ceilings Install Base StationsMount Base Stations on Finished Ceilings Install Outdoor Base Stations Wire outdoor Base StationsMount and connect outdoor Base Stations Power Up and Check Diagnostics System Initialization Page Voice-test each Base Station Test SystemRun Listen Verify Diagnostic Site Certification Page Site Preparation Checklist Installation FormsSpectraLink 6300 MCU Facility Preparation Shelf Number Interface Module Base Station Location WorksheetShelf Interface Module Extension Assignments WorksheetCustomer Acceptance Form SpectraLink 6300 MCU Facility Preparation Important Safety Information Safety NoticesPage Index OAI