SpectraLink 6300 MCU: Facility Preparation
unlimited access to the Customer Support Hotline for additional assistance.
Union labor
In some areas strict labor union rules will preclude the Polycom representative’s ability to install the equipment without union assistance. If such rules are in force in the local area, the customer must ensure that sufficient union help is available at the scheduled installation time to carry out the following functions:
•Install Base Stations
•Move and reinstall Base Stations
•Make cabling changes at
•Run cables
•Make and modify electrical connections
Prepare Location for Shelves
Polycom recommends an operational temperature range of 0º–
40º C
The MCU, composed of up to 20 shelves and one Intershelf Junction Panel, is usually installed in or near the telephone equipment room. If this is not possible, the MCU can be located anywhere that the telephone system lines are accessible.
The number and arrangement of the system shelves depends on the size and configuration of the system.
System Controller | Shelves | Base Stations | Users |
Part Number | Supported | Supported | Supported |
CSC301/ CSO301 | 1 | 60 | 160 |
CSC306/ CSO306 | 6 | 360 | 960 |
CSC320/ CSO320 | 20 | 1,000 | 3,200 |
|
|
|
|
Consideration should be given to:
•Environmental conditions. The system outputs 28 BTUs per hour, per interface module.
•Space for the backboard or rack.
22 | PN: |