SpectraLink 6300 MCU: Facility Preparation

5.Screw the protective cover onto the Base Station enclosure.

Power Up and Check Diagnostics

Turn the power switch in the upper left of the Primary and Expansion Shelves on.

After a slight delay, the lights on the cards will cycle through diagnostic tests.

After testing completes, lamp 1 should flash green, indicating that the card is running. If the Alarm light is red, there is a problem with the system. Refer to SpectraLink 6300 MCU: Maintenance and Diagnostics for troubleshooting information.

52

PN: 1725-36122-001_M.doc

Image 52
Contents SpectraLink 6300 MCU Installation Patent Information Polycom Model Numbers About This GuideRelated Documents Customer Support Icons and ConventionsContents System Installation Install Base StationsSite Certification Installation Forms System Initialization Test SystemIndex53H Page Installation Overview Installation Steps and Responsibilities Install Shelves and Interface ModulesSpectraLink 6000 System Description SpectraLink 6000 System Master Control Unit SpectraLink 6000 System ComponentsSpectraLink 6000 System topology Shelf 1 Primary Shelf Intershelf Junction Panel Shelf System Controller CSC or CSO301, 306,Expansion Shelf CSC300, CSO300 Interface Modules CPA, CPU, CPM, CPP, CPF316Base Stations Intershelf Junction Panel JPI300SpectraLink 6000 Wireless Telephones CcSpectraLink 6000 SystemOperator’s Console SpectraLink OAI GatewaySite Preparation Required Materials Provided by Customer Required hardwareSystem administrator Operator’s Console PCPrepare Location for Shelves Union laborPrepare rack or wall Rack mountingSpectraLink 6300 MCU Facility Preparation Wall mounting Wire specifications Prepare Power for ShelvesRun Cables to Base Station Locations Pull cable Terminate Cables at Base Station Locations Prepare Demarc Blocks Interface TypeMultiple power pairs Two-wire analog or digital interfaceFour-wire digital interface Program Telephone System Install Demarc BlocksAssign and program ports Site Preparation Two-wire analog or digital demarc block Telephone Ports Base Station Power Pairs DataFour-wire digital demarc block Base Station Power Pairs DataFour-wire Digital Connector B Connect demarc block 25-pair cable Page Facility Analysis System InstallationCheck Components SpectraLink 6300 MCU Facility Preparation Rack mount Install ShelvesWall mount Install Intershelf Junction Panel Connect Power to ShelvesConnect wire to terminals Run conduit to shelfInstall Cards Install Interface ModulesInstall Expansion Shelf Controllers CSC300 Do not install any card in slot 1 of expansion shelves Connect the Intershelf Junction Panel Connect Demarc Block RJ-21Cables to Interface Module Install Base Stations Mount Base Stations on Dropped Tile CeilingsMount Base Stations on Finished Ceilings Wire outdoor Base Stations Install Outdoor Base StationsMount and connect outdoor Base Stations Power Up and Check Diagnostics System Initialization Page Test System Voice-test each Base StationRun Listen Verify Diagnostic Site Certification Page Installation Forms Site Preparation ChecklistSpectraLink 6300 MCU Facility Preparation Base Station Location Worksheet Shelf Number Interface ModuleExtension Assignments Worksheet Shelf Interface ModuleCustomer Acceptance Form SpectraLink 6300 MCU Facility Preparation Safety Notices Important Safety InformationPage Index OAI