Test System

The system should now be tested to ensure that it is functioning correctly. Power cycle the system. Verify that all Base Stations download and go to a running status. This takes about 30 seconds after connecting the Base Station cable to the Base Station’s RJ-45 socket. During this period the Base Station’s LED will flash in several sequences. At the end of this period the LED will be flashing yellow.

Test each Base Station:

While standing near the Base Station, use a registered handset and go off-hook. Verify a clear dial tone. The Base Station’s LED should flash green.

Verify proper registration and operation of each handset by performing the following test:

1.Press the START key on each handset. The extension number should clear and you should hear dial tone. On some digital systems, depending on how the telephone system is programmed, you may have to select a line to get dial tone.

2.Place a call to each handset to verify ring, answer, clear transmit, and clear receive audio.

3.Verify all programmed features on each handset.

4.Press the END key. The line indicator should turn off.

Voice-test each Base Station

Walk around the installation site with a handset while making voice calls to a deskset. Verify that both ends of the conversation are of good quality on each Base Station.

PN: 1725-36122-001_M.doc

55

Image 55
Contents SpectraLink 6300 MCU Installation Patent Information Polycom Model Numbers About This GuideRelated Documents Icons and Conventions Customer SupportContents System Initialization Test System System InstallationInstall Base Stations Site Certification Installation FormsIndex53H Page Installation Overview Install Shelves and Interface Modules Installation Steps and ResponsibilitiesSpectraLink 6000 System Description SpectraLink 6000 System Master Control Unit SpectraLink 6000 System ComponentsSpectraLink 6000 System topology Shelf 1 Primary Shelf Intershelf Junction Panel Interface Modules CPA, CPU, CPM, CPP, CPF316 ShelfSystem Controller CSC or CSO301, 306, Expansion Shelf CSC300, CSO300Intershelf Junction Panel JPI300 Base StationsCcSpectraLink 6000 System SpectraLink 6000 Wireless TelephonesSpectraLink OAI Gateway Operator’s ConsoleSite Preparation Required hardware Required Materials Provided by CustomerOperator’s Console PC System administratorUnion labor Prepare Location for ShelvesRack mounting Prepare rack or wallSpectraLink 6300 MCU Facility Preparation Wall mounting Wire specifications Prepare Power for ShelvesRun Cables to Base Station Locations Pull cable Terminate Cables at Base Station Locations Interface Type Prepare Demarc BlocksTwo-wire analog or digital interface Multiple power pairsFour-wire digital interface Program Telephone System Install Demarc BlocksAssign and program ports Site Preparation Telephone Ports Base Station Power Pairs Data Two-wire analog or digital demarc blockBase Station Power Pairs Data Four-wire digital demarc blockFour-wire Digital Connector B Connect demarc block 25-pair cable Page Facility Analysis System InstallationCheck Components SpectraLink 6300 MCU Facility Preparation Rack mount Install ShelvesWall mount Connect Power to Shelves Install Intershelf Junction PanelRun conduit to shelf Connect wire to terminalsInstall Interface Modules Install CardsInstall Expansion Shelf Controllers CSC300 Do not install any card in slot 1 of expansion shelves Connect the Intershelf Junction Panel Connect Demarc Block RJ-21Cables to Interface Module Mount Base Stations on Dropped Tile Ceilings Install Base StationsMount Base Stations on Finished Ceilings Wire outdoor Base Stations Install Outdoor Base StationsMount and connect outdoor Base Stations Power Up and Check Diagnostics System Initialization Page Voice-test each Base Station Test SystemRun Listen Verify Diagnostic Site Certification Page Site Preparation Checklist Installation FormsSpectraLink 6300 MCU Facility Preparation Shelf Number Interface Module Base Station Location WorksheetShelf Interface Module Extension Assignments WorksheetCustomer Acceptance Form SpectraLink 6300 MCU Facility Preparation Important Safety Information Safety NoticesPage Index OAI