Chapter 3: Installation
3-1 Uncrating
1. Pry the crating away from the skid.
Note: Remove the nails holding the box to the skid and lift the box off carefully; avoiding staples in the 1’ x 4’ wood supports. Cut the steel banding.
2.Use a pry bar to remove the blocks securing the unit to the skid.
3.Lift unit from sides. Use a pry bar if necessary to carefully remove the skid from the unit.
4.Lower slowly.
3-2 Mounting the Control Panel
Note: Before you mount the panel, consider how you run wiring to the vacuum hoppers, the filter chamber atmospheric valve (if so equipped) and the pump motor starter(s), vacuum switch(es), and vent valve(s).
Mount the panel on a flat, vertical area. It should be a visible area that gives your operator access to the control. The panel requires a low voltage power drop as listed on the serial tag.
3-3 Electrical Connections
Refer to local electrical codes, the schematic and connection diagrams supplied with this unit and the serial tag for wiring considerations. Run all wiring in conduit if codes require it.
Making Control Panel Power Drop Wiring Connections
Hardwire the input power at 115/1/60 VAC or 220V/1/50 VAC, depending on the specifications, which are located on the Control Panel Serial Tag. The main power switch is located on the front of the enclosure.
Caution! We recommend that you protect PLC memory by providing the control panel with a dedicated circuit, a true earth ground, and a spike/surge protector.