System Diagnostics
During the unloaded exercise, the controller monitors the following data. The controller display indicates that the generator set is running, unless a fault is detected as described below.
D ATS connection. The controller verifies that the Model RXT ATS interface board is connected.
DBattery voltage. Battery voltage is checked before exercise to verify engine starting capability. Battery voltage provides a measurement of battery health. If the controller detects low battery voltage, the condition is indicated on the display.
D Communication integrity tests. J1939, RBUS, Ethernet, and USB are monitored for messages indicating that the controller and wiring are reliable.
D Engine speed. Engine speed is measured at reduced speed and full speed. An overspeed or underspeed condition will result in a fault condition and shutdown.
D Generator output frequency and voltage. Operating the generator at full speed allows the RDC2/DC2 controller to check the output power for correct voltage, frequency, and stability. When the engine is running at full speed, the controller verifies that the voltage and frequency are within acceptable limits. A fault message is displayed if the voltage or frequency is out of range.
D Oil pressure. Oil pressure is verified to ensure proper lubrication of critical engine components. Pressure is monitored at both reduced and full speeds. If the oil pressure is low, the Low Oil Pressure message is displayed and the generator set shuts down.
2.4.3Unloaded Full-Speed Exercise
The unloaded
To set an unloaded
2.4.4Loaded Full-Speed Exercise (with RXT only)
A loaded exercise starts the generator set, ramps up to full speed, and then transfers the electrical load from the utility source to the generator set. After 20 minutes, the load is transferred back to the utility source. The engine runs without load for 5 minutes or until cool, and then shuts down automatically.
Note: With a loaded exercise, power to the building is lost for up to 10 seconds during load transfer.
For a loaded exercise controlled by the RDC2 or DC2 controller, a Model RXT transfer switch must be connected to the generator set. To set a loaded exercise, follow the procedure in Figure
For a loaded exercise with a transfer switch other than a Kohlerr Model RXT, program the exercise at the transfer switch controller. Refer to the transfer switch operation manual for instructions.
2.4.5Power Failure During Exercise Cycle
If the utility power is lost during an unloaded exercise, the ATS transfers to the emergency source, the exercise is ended and the control remains in the AUTO mode.
If the utility power is lost during a loaded exercise, the exercise is ended. The ATS remains in the emergency position and the control goes into the AUTO mode.
The generator set continues to run and supply power to the load for the duration of the utility power outage. When Utility power is restored, the ATS will
Section 2 Generator Set Operation 23 |