If installing a grinding wheel for the first time, or when replacing a worn wheel, this section explains the order in which this process must take place. Every time a grinding wheel is removed from its hub, this procedure must be repeated. If installing a new wheel right out of the box, the ring (Page 23) test must also still be completed.

To remove and install a grinding wheel:

1.DISCONNECT MACHINE FROM POWER!

2.Place a sheet of plywood or similar on top of the table (see Figure 21), and open the grinding wheel cover.

4.Using the wrenches, loosen the retaining nut in the direction shown in Figure 23.

!

Hold

Figure 23. Removing wheel retaining nut.

5.Unthread the retaining nut (see Figure 24).

Plywood

!

Figure 21. Protecting table. Figure 24. Exposing wheel retaining washer.

3.Position the spindle wrenches on the spindle lug and the retaining nut (see Figure 22).

Retaining

Nut

6.Remove the retaining washer shown in Figure 25.

!

Spindle

Lug

Figure 22. Wheel retaining nut.

Figure 25. Wheel ready for removal.

-24-

Image 26
Contents 18 Surface Grinder Model SB1029Scope of Manual UpdatesCustomer Service Manual FeedbackTable of Contents Capabilities FeaturesAbout This Machine Identification IdentificationMachine Specifications Machine SpecificationsT R O D U C T I O N Basic Machine Safety Understanding Risks of MachineryF E T Y Additional Surface Grinder Safety Preparation Overview Things Youll NeedFull-Load Current Rating Power Supply RequirementsAvailability Circuit InformationExtension Cords For 220V Connection PrewiredGrounding Requirements For 440V ConnectionUnpacking InventoryBasic steps for removing rust preventative Cleaning & ProtectingBefore cleaning, gather the following Location Leveling Lifting & MovingLeveling & Mounting To assemble the machine AssemblyBolting to Concrete Floors Headstock elevation handwheel Initial Lubrication Power ConnectionInspections & Adjustments Test Run To test run your machineOperation Overview Controls Control panelGrit Size Wheel SelectionAbrasive Type GradeTo inspect a wheel for damage Wheel InspectionRing Test To perform a ring testRemoving & Installing Grinding Wheels To remove and install a grinding wheelWheel mounting hub Removing & Installing Wheel & Hub To remove and reinstall the wheel and hubPulling wheel hub Wheel Dressing To dress the grinding wheelWheel Balancing To balance the grinding wheelE R a T I O N Dust Port Positioning To adjust the dust port positionMagnetic Chuck Grinder OperationUsing the Surface Grinder Grinding TipsMaintenance Schedule Basic LubricationTo change the oil and adjust the flow rate Recommended OilsRemoving Table Backlash To remove table backlashTR O U B L E S H O OTI N G TR O U B L E S H O OTI N G Machine Storage To prepare your machine for storageElectrical Safety Instructions Wiring Diagram Color KEYTo convert the Model SB1029 to operate on Rewiring forHardwiring to Power Source 440VMotor 220V Electrical Components 220 VAC L15-15 PlugElectrical Box Contents 220V Electrical Box440V Electrical Components Oil Pump Motor SpindleElectrical Box Contents Electrical BoxColumn DescriptionElevation Control 125 109 108 110 111 123 121 113 101 112 107 106 124 126 Base 146Saddle Main Assembly List Tools Electrical Machine Labels 301Machine Labels List Rotation LabelT E S R R a N T Y Southbendlathe.com