AEG TKS-CS operating instructions ISO Small Distribution Box, Communication Interface PV.LoG-MH

Page 20

Compact Station TKS-CS - Operating Instructions

2.Establish the AC power connections and PE connections using the cable lug in accordance with the circuit diagram, and using the relevant tightening torque.

3.Remove any cable debris and tools from the equipment and replace the protective cover on the connection panel.

7.2.2ISO Small Distribution Box

 

5

1

6

 

7

2

8

3

4

5

Figure 14 - ISO small distribution box (example)

1

Residual-current-operated circuit-

5

Screw connections

breaker

6

Miniature circuit breakers

2

Back-up fuse sub-distribution

7

Fuses, max. 25 A

3

Terminal strips

8

Overvoltage protection

4Motor protection switch Auxiliary transformer

The ISO small distribution box is preinstalled in the compact station.

To open the ISO small distribution box, unscrew the four screw connections. The cover can then be pulled out towards the front.

Establish the connections in accordance with the circuit diagram.

7.2.3Communication Interface PV.LoG-MH

The communications cabinet PV.LoG-MH includes batteries, which are installed in the cabinet or in a separate box.

Install the communications cabinet PV.LoG-MH in accordance with the PV.LoG installation instructions. Wiring is carried out in accordance with the circuit diagram.

Data is exchanged between the PV.IcX combiner boxes or the PV.ControL and the PV.LoG-MH via CAN bus (*.USP and operating instructions for PV.LoG and PV.ControL).

Page 20 of 39

8000043213 BAL

Image 20
Contents TKS-CS Revision Service Status Revision Date NameTable of Contents Decommissioning and Dismantling Mailservice.aegpss@aegps.com General Information ValidityAppropriate Use List of AbbreviationsLightning Protection SafetyInstallation Location Scope of Delivery Available to orderEquipment Specifications StructureLow-Voltage Box DimensionsDimension AC Connections Low-voltage boxes exampleISO Small Distribution Box Communications Cabinet PV LoG-MH Central Earthing SystemMedium-Voltage System No. H07V-KNameTransformer 3 4 5 4Functional Description Transfer stationTransport Suspended loads during transportAssembly Setting in PlaceConnection Design Torque InstallationHinge side of the door when closing Communication Interface PV.LoG-MH Medium-voltage system example Medium-Voltage Transformer Tightening Torques for Screw Connections Working with voltages up to 1 kV Start-upOperation Servicing Contact with voltageResidual voltage from capacitors Contact with leakage currentEntry of water into electrical equipment Insufficient ventilation of equipmentHeat generation in resistors Obligation to Keep a Written Record Maintenance and Inspection Visual Inspection CleaningTesting/Measuring Functional TestRotating parts Care LubricationReplacing the Axial Ventilator Repairs Testing after RepairsReplacement Work Replacing the Transformer Roof structure Station frame Station roofReplacing the MV Switchgear Partial top view TKS-CS exampleMaintenance Schedule OngoingMonthly Every 6 monthsStoring Spare Parts AnnuallyEvery 2 years Every 4 yearsDismantling Decommissioning and DismantlingRemoving Connection Cables Disposal Statutory Provisions Chemical System ComponentsCompact Station TKS-CS Operating Instructions List of Tables List of Figures