AEG TKS-CS operating instructions Medium-Voltage System, No. H07V-KName

Page 14

Compact Station TKS-CS - Operating Instructions

No. H07V-KName

[mm2]

170 Low-voltage box

295 Cable entry

370 Station housing

4 16 Sub-distribution

516 Communications cabinet PV.LoG-MH

670 Medium-voltage system

770 Transformer

Table 3 - Potential equalising strip

The central earthing system is preinstalled on the potential equalising strip in the compact station.

4.4Medium-Voltage System

Figure 8 - MV switchgear (example)

The installed MV switchgear (example) is an interior system with cable branch line (K) and transformer branch line (T) modules. Further information on the MV switchgear is available in the installation and operating instructions included in the scope of delivery.

Page 14 of 39

8000043213 BAL

Image 14
Contents TKS-CS Revision Service Status Revision Date NameTable of Contents Decommissioning and Dismantling Mailservice.aegpss@aegps.com Appropriate Use General InformationValidity List of AbbreviationsLightning Protection SafetyInstallation Location Scope of Delivery Available to orderEquipment Specifications StructureLow-Voltage Box DimensionsDimension AC Connections Low-voltage boxes exampleISO Small Distribution Box Communications Cabinet PV LoG-MH Central Earthing SystemMedium-Voltage System No. H07V-KNameTransformer 3 4 5 4Functional Description Transfer stationTransport Suspended loads during transportAssembly Setting in PlaceConnection Design Torque InstallationHinge side of the door when closing Communication Interface PV.LoG-MH Medium-voltage system example Medium-Voltage Transformer Tightening Torques for Screw Connections Working with voltages up to 1 kV Start-upOperation Residual voltage from capacitors ServicingContact with voltage Contact with leakage currentEntry of water into electrical equipment Insufficient ventilation of equipmentHeat generation in resistors Obligation to Keep a Written Record Maintenance and Inspection Visual Inspection CleaningTesting/Measuring Functional TestRotating parts Care LubricationReplacing the Axial Ventilator Repairs Testing after RepairsReplacement Work Replacing the Transformer Roof structure Station frame Station roofReplacing the MV Switchgear Partial top view TKS-CS exampleMonthly Maintenance ScheduleOngoing Every 6 monthsEvery 2 years Storing Spare PartsAnnually Every 4 yearsDismantling Decommissioning and DismantlingRemoving Connection Cables Disposal Statutory Provisions Chemical System ComponentsCompact Station TKS-CS Operating Instructions List of Tables List of Figures