Compact Station
7.2.4Central Earthing System
Connect the active earthing to the potential equalising strip according to the circuit diagram.
7.2.5Medium-Voltage System
12
Figure 15 - Medium-voltage system (example)
1Cable branch line L1/L2/L3 (left flap), external AC connections
2Transformer branch line (right flap),
internal AC connections from transformer to load interrupter switch
The MV system is preinstalled in the compact station.
Use the power cables supplied for the system AC connections, and connect in accordance with the manufacturer's installation instructions located in the system. Insert the branch cable into the compact station from below.
8000043213 BAL | Page 21 of 39 |