AEG TKS-CS operating instructions Roof structure Station frame, Station roof

Page 32

Compact Station TKS-CS - Operating Instructions

1

2

3

Figure 19 - Station roof

 

 

1 Roof structure

 

3 Station frame

2Screw connection

iThe roof structure weighs around 130 kg. Comply with Directive 90/269/EEC (handling of loads).

3.Open all doors and unscrew the 6 roof structure screw connections. Completely remove the roof structure from the compact station TKS.CS (roof removal: Bosecker).

1

2

3

Figure 20 - Replacing the transformer, 2 (example)

1 Low-voltage box

3 Transformer compartment

2Transformer

4.Attach the transformer to the transport eyelets and carefully lift it using lifting gear.

Page 32 of 39

8000043213 BAL

Image 32
Contents TKS-CS Revision Service Status Revision Date NameTable of Contents Decommissioning and Dismantling Mailservice.aegpss@aegps.com General Information ValidityAppropriate Use List of AbbreviationsLightning Protection SafetyInstallation Location Scope of Delivery Available to orderEquipment Specifications StructureLow-Voltage Box DimensionsDimension AC Connections Low-voltage boxes exampleISO Small Distribution Box Communications Cabinet PV LoG-MH Central Earthing SystemMedium-Voltage System No. H07V-KNameTransformer 3 4 5 4Functional Description Transfer stationTransport Suspended loads during transportAssembly Setting in PlaceConnection Design Torque InstallationHinge side of the door when closing Communication Interface PV.LoG-MH Medium-voltage system example Medium-Voltage Transformer Tightening Torques for Screw Connections Working with voltages up to 1 kV Start-upOperation Servicing Contact with voltageResidual voltage from capacitors Contact with leakage currentEntry of water into electrical equipment Insufficient ventilation of equipmentHeat generation in resistors Obligation to Keep a Written Record Maintenance and Inspection Visual Inspection CleaningTesting/Measuring Functional TestRotating parts Care LubricationReplacing the Axial Ventilator Repairs Testing after RepairsReplacement Work Replacing the Transformer Roof structure Station frame Station roofReplacing the MV Switchgear Partial top view TKS-CS exampleMaintenance Schedule OngoingMonthly Every 6 monthsStoring Spare Parts AnnuallyEvery 2 years Every 4 yearsDismantling Decommissioning and DismantlingRemoving Connection Cables Disposal Statutory Provisions Chemical System ComponentsCompact Station TKS-CS Operating Instructions List of Tables List of Figures