AEG TKS-CS Installation, Hinge side of the door when closing, Connection Design Torque

Page 19

Compact Station TKS-CS - Operating Instructions

7.2Installation

WARNING

Hinge side of the door when closing

Fingers or hands may be crushed.

Do not hold the hinge side of the door.

Take care while closing the cabinet door.

iObserve the bending radius of the supply lines. With one bend:

bending radius = 10 x diameter of supply line.

7.2.1Low-Voltage Box

1

2

3

4

5

Figure 13 - LV box

 

 

1

LV box protective cover

4

Cable lug

2

Load interrupter NH4 - 1250 A

5

Protective cover

3Connection panel NH4 (Cu busbars)

Connection

Design

*)

Torque

 

 

 

(Nm)

L1-3:U, V, W

max. 3x240 mm2, M12

2

15.5

PE

max. 3x120 mm2, M12

2

15.5

*) 2 = cable lug connection

Table 4 - LV box connections

1.Remove the protective cover from the connection panel.

iThe order of the conductors (L1, L2, L3) must be adhered to.

8000043213 BAL

Page 19 of 39

Image 19
Contents TKS-CS Status Revision Date Name Revision ServiceTable of Contents Decommissioning and Dismantling Mailservice.aegpss@aegps.com List of Abbreviations General InformationValidity Appropriate UseInstallation Location SafetyLightning Protection Available to order Scope of DeliveryStructure Equipment SpecificationsDimension DimensionsLow-Voltage Box Low-voltage boxes example AC ConnectionsISO Small Distribution Box Central Earthing System Communications Cabinet PV LoG-MHNo. H07V-KName Medium-Voltage System3 4 5 4 TransformerTransfer station Functional DescriptionSuspended loads during transport TransportSetting in Place AssemblyHinge side of the door when closing InstallationConnection Design Torque Communication Interface PV.LoG-MH Medium-voltage system example Medium-Voltage Transformer Tightening Torques for Screw Connections Operation Start-upWorking with voltages up to 1 kV Contact with leakage current ServicingContact with voltage Residual voltage from capacitorsHeat generation in resistors Insufficient ventilation of equipmentEntry of water into electrical equipment Obligation to Keep a Written Record Cleaning Maintenance and Inspection Visual InspectionFunctional Test Testing/MeasuringReplacing the Axial Ventilator Care LubricationRotating parts Replacement Work Replacing the Transformer Testing after RepairsRepairs Station roof Roof structure Station framePartial top view TKS-CS example Replacing the MV SwitchgearEvery 6 months Maintenance ScheduleOngoing MonthlyEvery 4 years Storing Spare PartsAnnually Every 2 yearsRemoving Connection Cables Decommissioning and DismantlingDismantling Chemical System Components Disposal Statutory ProvisionsCompact Station TKS-CS Operating Instructions List of Figures List of Tables