AEG operating instructions Replacing the MV Switchgear, Partial top view TKS-CS example

Page 33

Compact Station TKS-CS - Operating Instructions

5.Place a new transformer in the compact station's trough and establish the connections. Finally, replace and align the roof structure, and establish the screw connections (transformer operating instructions).

10.3.2.2Replacing the MV Switchgear

12

 

3

4

 

Figure 21 - Partial top view TKS-CS (example)

1

Transformer compartment

3

Medium-voltage compartment

2

Low-voltage box

4

MV switchgear

1.Disconnect the equipment safely.

2.Remove all connections from the MV switchgear, and secure the equipment.

3.Unscrew the screws of the MV switchgear and remove it from the compact station using an industrial truck (MV switchgear BAL).

8000043213 BAL

Page 33 of 39

Image 33
Contents TKS-CS Status Revision Date Name Revision ServiceTable of Contents Decommissioning and Dismantling Mailservice.aegpss@aegps.com Validity General InformationAppropriate Use List of AbbreviationsSafety Installation LocationLightning Protection Available to order Scope of DeliveryStructure Equipment SpecificationsDimensions DimensionLow-Voltage Box Low-voltage boxes example AC ConnectionsISO Small Distribution Box Central Earthing System Communications Cabinet PV LoG-MHNo. H07V-KName Medium-Voltage System3 4 5 4 TransformerTransfer station Functional DescriptionSuspended loads during transport TransportSetting in Place AssemblyInstallation Hinge side of the door when closingConnection Design Torque Communication Interface PV.LoG-MH Medium-voltage system example Medium-Voltage Transformer Tightening Torques for Screw Connections Start-up OperationWorking with voltages up to 1 kV Contact with voltage ServicingResidual voltage from capacitors Contact with leakage currentInsufficient ventilation of equipment Heat generation in resistorsEntry of water into electrical equipment Obligation to Keep a Written Record Cleaning Maintenance and Inspection Visual InspectionFunctional Test Testing/MeasuringCare Lubrication Replacing the Axial VentilatorRotating parts Testing after Repairs Replacement Work Replacing the TransformerRepairs Station roof Roof structure Station framePartial top view TKS-CS example Replacing the MV SwitchgearOngoing Maintenance ScheduleMonthly Every 6 monthsAnnually Storing Spare PartsEvery 2 years Every 4 yearsDecommissioning and Dismantling Removing Connection CablesDismantling Chemical System Components Disposal Statutory ProvisionsCompact Station TKS-CS Operating Instructions List of Figures List of Tables