BGV A2 requires the owner to perform repeat tests at stipulated times in order to verify that the electrical equipment is in perfect working order.

At stipulated times, the owner must check that the fault current, differential current and fault voltage protection devices are functioning properly.

Carry out manual insulation testing.

10.2.5Care

10.2.5.1 Lubrication

Carry out the following care measures for the station:

Lubricate hinges, rods and guide rails after cleaning.

Lubricate the ball bearings in the axial ventilator after around 20,000 operating hours or a maximum of 4 years, according to the manufacturer's specifications.

10.2.5.2Replacing the Axial Ventilator

WARNING

Rotating parts

Injury to fingers and hands possible.

Do not reach into rotating parts.

De-energise fans.

1

2

3

4

5

 

6

Figure 17 - Replacing the axial ventilator

 

 

1

Housing plate with M9

 

4

Connection cable with seal

2

Protective screen

 

5

Drive motor

3

Impeller

 

 

 

6

Weather-proof cover

The axial ventilator must be replaced if it is defective or runs out of round. As a precaution, it should be changed every 4 years (when bearing lubrication is due).

Remove the axial ventilator in accordance with the manufacturer's specifications and send it to the manufacturer for maintenance.

Page 30 of 39

8000043213 BAL

Image 30
Contents TKS-CS Revision Service Status Revision Date NameTable of Contents Decommissioning and Dismantling Mailservice.aegpss@aegps.com Appropriate Use General InformationValidity List of AbbreviationsSafety Installation LocationLightning Protection Scope of Delivery Available to orderEquipment Specifications StructureDimensions DimensionLow-Voltage Box AC Connections Low-voltage boxes exampleISO Small Distribution Box Communications Cabinet PV LoG-MH Central Earthing SystemMedium-Voltage System No. H07V-KNameTransformer 3 4 5 4Functional Description Transfer stationTransport Suspended loads during transportAssembly Setting in PlaceInstallation Hinge side of the door when closingConnection Design Torque Communication Interface PV.LoG-MH Medium-voltage system example Medium-Voltage Transformer Tightening Torques for Screw Connections Start-up OperationWorking with voltages up to 1 kV Residual voltage from capacitors ServicingContact with voltage Contact with leakage currentInsufficient ventilation of equipment Heat generation in resistorsEntry of water into electrical equipment Obligation to Keep a Written Record Maintenance and Inspection Visual Inspection CleaningTesting/Measuring Functional TestCare Lubrication Replacing the Axial VentilatorRotating parts Testing after Repairs Replacement Work Replacing the TransformerRepairs Roof structure Station frame Station roofReplacing the MV Switchgear Partial top view TKS-CS exampleMonthly Maintenance ScheduleOngoing Every 6 monthsEvery 2 years Storing Spare PartsAnnually Every 4 yearsDecommissioning and Dismantling Removing Connection CablesDismantling Disposal Statutory Provisions Chemical System ComponentsCompact Station TKS-CS Operating Instructions List of Tables List of Figures