HP Performance Optimized Data Center (POD) 240a Overview, About this document, Site assessment

Page 5

Overview

About this document

This document outlines the site requirements for an HP Performance Optimized Datacenter (POD) 240a. The customer must provide a qualified architectural or consulting engineering team to generate site-specific documents for each HP POD 240a installation, including final site drawings. The customer's site installation design must comply with all local and national regulations, ordinances, codes, and the specifications listed in this document.

Site assessment

HP requires a detailed site assessment prior to planning and preparing the customer site location for the HP POD 240a. Consult with HP to schedule a site assessment.

For more information, see the Site Assessment Checklist in the HP Performance Optimized Datacenter (POD) 240a Site Preparation Guide.

Overview 5

Image 5
Contents Part Number October Edition Page Contents Fire, safety, and security notifications Site assessment OverviewAbout this document HP Site Preparation Drawing Package Site requirementsSite preparation Early infrastructure requirementsOther structures Site padSpace requirements and clearances HP POD 240a dimensions and required clearancesEnd 2 view clearances shown Side view clearances shown HP POD 240a and support equipment sample offload plan HP POD 240a weightFuture expansions Site space and clearance requirementsAdditional equipment space requirements Suggested assembly installation equipment Preparing for delivery and assemblySafety for assembly Shipping considerationsStorage requirements Temporary lighting and powerAssembly prerequisites Environmental considerations Areas prone to lightning or power surgesEnvironmental considerations Cold weatherProximity to utilities and drains UtilitiesSystem utilities Water supplyWater quality DrainagePower requirements PowerPreparing the site for power Connections to central facility infrastructure Required facility connectionsNetwork connections Connection portalsGrounding requirements Grounding pad End view shown Component Humidifier Supported facility connectionsHP POD 240a security Fire, safety, and security notificationsAHJ GlossaryNEC
Related manuals
Manual 8 pages 155 b Manual 39 pages 18.56 Kb Manual 93 pages 30.86 Kb