HP Performance Optimized Data Center (POD) 240a manual Site pad, Other structures

Page 7

Operational clearance around the HP POD 240a

Power (on page 17)

Water supply (on page 15)

Drainage (on page 16)

Site pad (on page 7)

Other structures (on page 7)

Site pad

The structural design of the HP POD 240a site pad design is based on specific weight load locations, accounting for the HP POD 240a structural footing and supported IT infrastructure.

Other structures

If a customer-provided vestibule or other structure will be installed at the HP POD 240a site, the following specifications must be maintained:

Flashing must be installed to the exterior of the HP POD 240a in the location where the other structure will be attached to protect the HP POD 240a and ensure a waterproof barrier.

Access catwalks and/or landings might be required to maintain the required egress from the HP POD 240a HVAC/DX service area.

Access catwalks and/or landings might be required to maintain the required access to the HP POD 240a electrical panels.

Site requirements 7

Image 7
Contents Part Number October Edition Page Contents Fire, safety, and security notifications About this document OverviewSite assessment Early infrastructure requirements Site requirementsHP Site Preparation Drawing Package Site preparationOther structures Site padSpace requirements and clearances HP POD 240a dimensions and required clearancesEnd 2 view clearances shown Side view clearances shown HP POD 240a and support equipment sample offload plan HP POD 240a weightAdditional equipment space requirements Site space and clearance requirementsFuture expansions Shipping considerations Preparing for delivery and assemblySuggested assembly installation equipment Safety for assemblyAssembly prerequisites Temporary lighting and powerStorage requirements Cold weather Areas prone to lightning or power surgesEnvironmental considerations Environmental considerationsWater supply UtilitiesProximity to utilities and drains System utilitiesWater quality DrainagePower requirements PowerPreparing the site for power Connection portals Required facility connectionsConnections to central facility infrastructure Network connectionsGrounding requirements Grounding pad End view shown Component Humidifier Supported facility connectionsHP POD 240a security Fire, safety, and security notificationsAHJ GlossaryNEC