HP Performance Optimized Data Center (POD) 240a manual Power, Drain locations

Page 13

Do not use well water, industrial water, water from cooling circuits, or water contaminated by any chemicals or bacteria.

Do not add disinfectants or anticorrosive compounds to the water, which are potential irritants.

HP highly recommends installing a filter to be sure that water is free of particles.

Drain locations

The following figure shows the drain locations on the HP POD 240e NA.

Side view shown

Callout

Component

Description

Quantity per

Total quantity

 

 

 

side

per HP POD

 

 

 

 

240e NA

 

 

 

 

 

1

Adiabatic media

Removes excess water from the

2

4

 

drain

adiabatic media drip tray

 

 

2

Rain water drain

Removes rain water from the HP POD

2

4

 

 

240e NA

 

 

IMPORTANT: Consult with your AHJ to determine the appropriate drainage system routing.

Power

Site requirements 13

Image 13
Contents Abstract Page Contents Contacting HP Overview Safety and NEC complianceAbout this document Site assessment Site safety and securitySite preparation Fire detectionDimensions and required clearances Weight requirementsSite requirements Site padSite requirements Future expansions Racks Grounding requirements Cold aisle clearanceGrounding electrode System utilities UtilitiesDrain locations PowerSite electrical system Transformers and switchboards Environmental control system Supported facility connectionsConnections to central facility infrastructure Connection portalsECS EPO Fire box Demarcation boxFire, safety, and access notifications Access controlSupported facility connections Environmental considerations Areas prone to lightning or power surgesEnvironmental risks Cold weatherCompleting a site assessment Site plan requirements and actionsHP Site Preparation Drawing Package Zoning and permit requirementsSite planning InstallationLifting requirements Storage requirements Appendix a HP site assessment HP POD 240e NA site assessment checklistDescription Yes Initial Description Initial Installation prerequisites HP POD 240e NA site readiness checklistAppendix B Preparing for delivery Pre-delivery tasksWater supply Adiabatic media water supply Description Sign-off Before you contact HP Contacting HPHP contact information Regulatory compliance notices Safety and NEC complianceHP POD 240e NA regulatory compliance Warranty information Safety and regulatory complianceEPO GlossaryPPE UPS Documentation feedback Index Index
Related manuals
Manual 8 pages 155 b Manual 26 pages 60.09 Kb Manual 93 pages 30.86 Kb