Item | Description | Yes | No | N/A |
| Initial |
| |
|
|
|
|
|
|
|
| |
11. Support | Physically evaluate the delivery path that is required with the |
|
|
|
|
|
| |
infrastructure for | customer's site engineering personnel to identify any |
|
|
|
|
|
| |
access requirements | obstacles that might be encountered during the site visit. |
|
|
|
|
|
| |
12. Site engineering | Review and document the following items with the site |
|
|
|
|
|
| |
review | engineering personnel: |
|
|
|
|
|
| |
| • | Delivery |
|
|
|
|
|
|
| • | Staging |
|
|
|
|
|
|
| • | Installation |
|
|
|
|
|
|
| • | Utilities |
|
|
|
|
|
|
| • | Commissioning requirements |
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
13. Capacity of | Review the electrical requirements of the HP POD 240e NA |
|
|
|
|
|
| |
electrical | with the customer and the customer's site engineering |
|
|
|
|
|
| |
infrastructure | personnel. |
|
|
|
|
|
| |
| HP is not responsible for customer site infrastructure unless it |
|
|
|
|
|
| |
| is stated in the SOW. |
|
|
|
|
|
| |
14. Adiabatic | Determine pressure, temperature, instantaneous flow rate, |
|
|
|
|
|
| |
media water | type, and source of the proposed media water. Be sure the |
|
|
|
|
|
| |
| site parameters are within or will be within specifications |
|
|
|
|
|
| |
| before installation. |
|
|
|
|
|
| |
15. Access control | Review site access and security procedures with the |
|
|
|
|
|
| |
| customer's site engineering personnel. Be sure sufficient |
|
|
|
|
|
| |
| access is available to HP's installation team. |
|
|
|
|
|
| |
16. | Following the HP installation site visit, analyze the data that is |
|
|
|
|
|
| |
Recommendations | collected and prepare a report of findings. HP must identify |
|
|
|
|
|
| |
| potential obstacles to installation and make |
|
|
|
|
|
| |
| recommendations for any additional testing or changes to |
|
|
|
|
|
| |
| the installation plan. |
|
|
|
|
|
| |
Customer responsibilities |
|
|
|
|
|
| ||
|
|
|
|
|
| |||
Item | Description |
|
|
| Initial |
| ||
|
|
|
|
| ||||
1. Point of contact | Provide HP with the name and telephone number of the designated point of |
|
|
| ||||
information | contact for the purposes of this service. |
|
|
|
|
|
| |
2. Service listing | Provide all information that is required under this service listing or reasonably |
|
|
| ||||
information | determined by HP to be necessary to deliver the service, including but without |
|
|
| ||||
| limitation, any documentation (internal or external) regarding prior plans or |
|
|
| ||||
| investigations used to identify the proposed installation site. |
|
|
|
|
|
| |
3. Timely response | Provide a timely response (such as, in a time period that does not adversely |
|
|
| ||||
| affect the HP scheduled performance of the service) to all requests for |
|
|
| ||||
| information by HP. |
|
|
|
|
|
| |
4. Access to subject | Provide HP access to all subject areas and support areas, including the |
|
|
| ||||
areas and support | proposed installation site and the mechanical or electrical infrastructure |
|
|
| ||||
areas | provided to support the HP POD 240e NA. |
|
|
|
|
|
| |
5. Badge access | Provide HP badge access or an escort for the duration of the site visit to |
|
|
| ||||
| facilitate required access to all necessary areas. |
|
|
|
|
|
| |
6. Site engineering | Be sure that your site engineering personnel are familiar with the proposed |
|
|
| ||||
personnel | installation site. The personnel that are responsible for the maintenance and |
|
|
| ||||
| support of the existing infrastructure must be available to answer questions. |
|
|
| ||||
7. Documentation | Provide HP with copies of all available mechanical and electrical system |
|
|
| ||||
| design documentation, including |
|
|
| ||||
| drawings. As appropriate to the specific location, provide HP with campus |
|
|
| ||||
| maps, building drawings, floor plans, and other relevant prints to assist in the |
|
|
| ||||
| documentation and evaluation of the proposed installation site. |
|
|
| ||||
|
| Appendix A: HP site assessment 26 |